Allen Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
novembre 032017

Cedarvale and Forest Hill Stations Open House

Thank you for attending the open house about Cedarvale and Forest Hill Stations on November 2, 2017. 

For those of you who missed it, the presentation is here: Lire la suite »

novembre 022017

Overnight Watermain Works on Eglinton Avenue at Allen Road for Cedarvale Station

WHAT WORK IS TAKING PLACE?

  • In preparation for the next phase of shoring works at Cedarvale Station, crews need to cap and remove an old watermain that runs under the current Eglinton Avenue westbound lane.
  • Crews will be occupying a lane on Eglinton Avenue West from Park Hill Road to Allen Road North (in front of the TTC station) to accommodate this work.

TIMING Lire la suite »

octobre 262017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on October 25, 2017. You can see the presentation here:

Lire la suite »

octobre 242017

Early Morning Concrete Pour at Cedarvale Station for Crossover Track Roof Construction

WHAT WORK IS TAKING PLACE?

  • With the invert concrete slab now complete at the crossover track section east of Cedarvale Station, the next phase is pouring the roof slab. The roof slab will be poured in sections. 
  • Due to the large size of these concrete pours, work will start at 4AM in order to complete the pour during the daytime hours, avoiding late overnight work. 
  • The first pour was successfully completed on October 12.

TIMING Lire la suite »

octobre 242017

Allen Road - Short Duration Rolling Lane Reductions - October 27

What Work is Taking Place?

  • Crews need to complete surveying activities for centre lines on Allen Road from Eglinton Avenue West to the Aldburn Road Bridge.
  • For two hours, one in each direction (north and south), Allen Road will have rolling lane reductions.

Timing Lire la suite »

octobre 232017

Eglinton Lane Reduction for Cedarvale Station Utility Work

What Work is Taking Place?

  • To accommodate the continued utility works for Cedarvale Station, crews will reduce eastbound Eglinton Avenue from Park Hill Road to Allen Road to one lane to access two maintenance manholes.

Timing

  • The lane reduction is scheduled for October 23 – 27 from 10:00 AM to 3:00 PM daily to reduce impact on peak traffic hours.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

What to Expect

  • Eglinton Avenue will be reduce
octobre 182017

Preparing to Realign Allen Road South

PREPARING TO REALIGN ALLEN ROAD SOUTH

In early 2018, the construction work zones and traffic set up will change again for the next phase of support of excavation (shoring) activities on the north side of Eglinton Avenue West at Allen Road.

This requires the Allen Road South off-ramp to be realigned approximately 20m west.

The existing All Road South off-ramp will be in place as-is until early 2018.


What Work is Taking Place? Lire la suite »

octobre 062017

Overnight and Early Morning Works at Cedarvale Station for Roof Slab Concrete Pour and Traffic Deck Coating

What Work is Taking Place?

 

  • Next week, two nights of overnight work are required and one early morning concrete pour is planned.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Traffic Deck Coating

TUESDAY OCTOBER 10 at 7PM – WEDNESDAY OCTOBER 11 at 5AM

WEDNESDAY OCTOBER 11 at 7PM – THURSDAY OCTOBER 12 at 5AM

  Lire la suite »

septembre 292017

Cedarvale Station: Overnight Crosswalk Line Painting & Road Decking Inspection - Oct 1 & Oct 2

What Work is Taking Place?

  • Two nights of overnight work on Eglinton Avenue West at Allen Road are required.
  • Work will be done overnight while traffic volumes are low.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Crosswalk Line Painting

MIDNIGHT on SUNDAY, OCTOBER 1 until APPROXIMATELY 2AM on MONDAY, OCTOBER 2 Lire la suite »

septembre 282017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on September  27, 2017. You can see the presentation here: Lire la suite »