Allen Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
août 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Lire la suite »

août 252017

Cedarvale Station: Road Closures for Utility Relocation & Support of Excavation

Updated: August 25, 2017
Original Issue Date: June 28, 2017

What Work is Taking Place?

The Cedarvale Station work zones are now in full swing as crews complete tunnel concrete pours, utility relocation, and support of excavation activities.

To continue to relocate and upgrade storm and sanitary sewer infrastructure and complete support of excavation, traffic changes in the vicinity of Cedarvale Station are required.

Throughout the Summer 2017, the following roads were closed at Eglinton Avenue West: Lire la suite »

juillet 272017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on July 26, 2017. You can see the presentation here:

Lire la suite »

juillet 192017
juin 292017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on June 28, 2017. You can see the presentation here:

juin 222017

Storm Sewer Connection in Cedarvale Park

What Work is Taking Place?

In preparation for the construction of Cedarvale Station, several storm and sanitary sewers must be reconfigured prior to the commencement of the support of excavation works. As part of one of these relocations, an existing connection must be enabled in one of the storm sewers at Cedarvale Park.

Crews will occupy a small portion of the park in the vicinity of an existing manhole (see picture below) in order to conduct the works.

Timing Lire la suite »

juin 092017

UPDATE: Cedarvale Station Support of Excavation

Original issue date: March 14, 2017
Re-issue date: June 9, 2017

UPDATE: Cedarvale Station Support of Excavation

By the end of 2015, tunneling works in the vicinity of Allen Road had concluded. Throughout 2016 and the beginning of 2017, crews conducted preparatory works for the future Cedarvale Station construction. Lire la suite »

juin 012017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on May 31, 2017. You can see the presentation here:

Lire la suite »