octobre 072015

Monitoring Equipment Installation in the vicinity of Eglinton Avenue West and Vesta Drive

What: Monitoring equipment will be installed on Eglinton Avenue West in the vicinity of Vesta Drive. This equipment will measure important data related to the work of our tunnel boring machines underground. These measurements will allow construction crews to adjust tunnelling activities along Eglinton Avenue West if needed.  

monitoring equipment installation Oct 2015 Lire la suite »

octobre 052015

Eglinton Crosstown Construction Update

Metrolinx is making progress on the Crosstown project. Construction of a launch shaft east of Brentcliffe Road is complete and assembly of two tunnel boring machines (TBMs) is nearing completion. Utility relocation and headwall construction along Eglinton Avenue East between Brentcliffe and Bayview started in January 2014. Some works along the road have been completed and others are progressing well. The Crosstown Team appreciates the patience of our neighbours while we work to build transit. Lire la suite »

octobre 022015

Short- term Road Closures at Gilgorm Road for Removal of Grout Plant

What: The jet grout plant at Eglinton Avenue West and Gilgorm Road will no longer be needed and will be taken down over the next few weeks. This will result in road closures at the south end of Gilgorm Road. 

When: The demobilization of the plant has started and will continue over the next couple of weeks. The road closure is expected to start as early as October 2 and last for approximately six days. The site will no longer occupy the south end of Gilgorm Road after October 9.   Lire la suite »

octobre 012015

Eglinton Crosstown Line Station and Stop Names

The Eglinton Crosstown Project is building the Eglinton Line, a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilometre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today.    Lire la suite »

septembre 252015

East tunnel boring machines begin their journey!

The Eglinton Crosstown LRT tunnel boring machines 'Don' and 'Humber' will begin their journey westward on September 29, 2015, marking another milestone toward the completion of the new LRT. 

The westbound tunnelling will start from the launch shaft located east of Brentcliffe Rd. and will proceed towards Yonge St. Work on the western segment of the tunnel has been underway since June 2013 with four of the 6.5 kilometres already complete. All tunnelling work is expected to be finished by the end of 2016. Lire la suite »

septembre 032015

Monitoring Equipment Installation at intersection of Avenue Road and Eglinton Avenue West

Friday September 4 and Tuesday September 8 2015

What: Crews will continue installing monitoring equipment at the intersection of Avenue Road and Eglinton Avenue West. This equipment will measure important data related to the work of our tunnel boring machines underground.

Where: The equipment will continue to be installed within the roadway along Eglinton Avenue West and Avenue Road.

When: Specifically for the intersection of Avenue Road and Eglinton Avenue West of the monitoring equipment will be installed: Lire la suite »

août 212015

Partial Road Closure for Gilgorm Road

Starting the week of August 24, 2015

What work is starting?

What: Enbridge Gas Distribution (Enbridge) will need to close the south end of Gilgorm Road (at Eglinton Avenue West) in order to complete the relocation of natural gas pipelines.

partial road closure gilgorm august 2015 Lire la suite »

août 172015

Monitoring Equipment Installation along Eglinton Avenue East at Avenue Road

What: Monitoring equipment will continue to be installed at major intersections along Eglinton Avenue East. This equipment will measure important data related to the work of our tunnel boring machines underground. These measurements will allow construction crews to adjust tunnelling activities along Eglinton Avenue East if needed.   Lire la suite »

juillet 152015

UPDATE: Avenue Station Headwall Construction

What: In this phase of construction, crews are building the headwalls for the future Avenue Station. Headwalls are underground support walls located at the east and west ends of the station location.  Lire la suite »