Demolition Work at Future Leaside (formerly Bayview) Station

What work is starting?

In February 2016, crews began conducting preparatory activities in the Bayview Avenue and Eglinton Avenue East vicinity to make way for the future Leaside Station. 

Upcoming Works – Demolition Lire la suite »

février 122016

Next Stage: Bayview Headwall Construction – Shift to South Side and Middle Lanes on Eglinton Avenue East

What work is starting?

What: Crews will continue constructing the east and west headwalls for the future Bayview Station in advance of the tunnelling works.  On the east side of Bayview Avenue, crews will be shifting construction to the middle lanes on Eglinton Avenue East. On the west side of Bayview Avenue, crews will be shifting construction to the south side of Eglinton Avenue East. Lire la suite »

janvier 222016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

Dear Neighbour, 

As you know, tunnelling for the Eglinton Crosstown light rail transit (LRT) line will continue through 2016. Metrolinx has sent various updates related to the tunnelling work and its progress; however, regrettably less time has been spent to communicate some of the impacts of preparatory or pre-tunnelling work that is required in advance of tunnel boring machines passing through a particular area.  Lire la suite »

janvier 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Lire la suite »

janvier 142016

Stage 2: Bayview Headwall Construction – Shift to North Side of Eglinton Avenue East

What work is starting?

What: Crews will be shifting construction to the north lanes on Eglinton Avenue East to continue constructing the east and west headwalls for the future Bayview Station in advance of the tunnelling works.  Lire la suite »

janvier 082016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

What: To prepare for west headwall construction for the future Bayview Station, crews are rehabilitating and upgrading an existing underground sewer on Eglinton Avenue East between east of Banff Road and west of Bayview Avenue. 

When: Work began in December, 2015, and will continue for several weeks. Work may be rescheduled or adjusted due to weather conditions or unforeseen circumstances.

Please be advised:  Lire la suite »

janvier 082016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

What: To prepare for west headwall construction for the future Bayview Station, crews are rehabilitating and upgrading an existing underground sewer on Eglinton Avenue East between east of Banff Road and west of Bayview Avenue. 

When: Work began in December, 2015, and will continue for several weeks. Work may be rescheduled or adjusted due to weather conditions or unforeseen circumstances.

Please be advised:  Lire la suite »

décembre 072015

OVERNIGHT CONSTRUCTION AT BAYVIEW/EGLINTON INTERSECTION

What work is starting?

What: Installation of a jet-grout delivery trench within the intersection of Bayview Avenue and Eglinton Avenue.

When:   Lire la suite »

novembre 242015

Temporary Sewer Work - Walder Avenue

What work is starting?

What: In conjunction with the nearby Eglinton Avenue East sewer rehabilitation work, crews will be excavating for temporary bypass pipes on the west side of Walder Avenue in the southbound lane.  

Why:  A major sewer under Eglinton Avenue East requires upgrading prior to tunnel excavation. Lire la suite »

novembre 052015

Tunnelling for the Crosstown: What you may experience

As you know, tunnelling continues on the Eglinton Crosstown Light Rail Transit (LRT) project as we build the underground portion of the future transit line. 

The tunnel boring machines (TBMs) operate around the clock - 24 hours a day, seven days week. On average, they each travel about 10 metres per day. Our TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area.    Lire la suite »