Update: Extended Sidewalk Closure for Subsurface Utility Investigation Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting subsurface utility investigation along Eglinton Avenue East between Birchmount Road and Rosemount Drive. Work began in November 2018 and will be extended until the end of March 2019. There will be sidewalk closure on the north side of Eglinton Avenue East in close proximity to 2306 Eglinton Avenue East in order to safely carry out the work.  Lire la suite »

mars 042019

Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the centre of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as mid-March 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.

Stage 2 Lire la suite »

février 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Lire la suite »

janvier 312019

Updated: Hydro Utility Relocation between Birchmount Road to Kennedy Road

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Lire la suite »

janvier 292019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on January 29, 2019. You can see the presentation here:

Lire la suite »

janvier 182019

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

Telecom work has been extended until the Spring 2019.

Lire la suite »

décembre 042018

Sidewalk Closure at Rosemount Drive and Eglinton Avenue East to Support Subsurface Utility Investigation Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting subsurface utility investigation along Eglinton Avenue East between Birchmount Road and Rosemount Drive.

Work began as early as November 26th. There will be sidewalk closure on the north side of Eglinton Avenue East near 2306 Eglinton Avenue East in order to safely carry out the work. Lire la suite »

décembre 042018

Investigation of Underground Utilities between Birchmount Road and Rosemount Drive

What Work is Taking Place?

In support of construction of the future At-Grade stops, crews will be conducting subsurface utility engineering (SUE) investigation work along Eglinton Avenue East between Birchmount Road and Rosemount Drive.

Crews will drill bore holes and use a hydro-vacuum truck within the City’s right-of-way and roadway to determine the location and depth of existing underground utilities for design purposes. Lire la suite »

novembre 302018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Birchmount Road to Rosemount Drive

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting wet utilities relocation work along Eglinton Avenue East between Birchmount Road and Rosemount Drive. Starting as early as December 3, 2018 and lasting approximately four (4) months, crews will install new pipes, and replace manholes and catch basins. The work will be conducted in stages.

Stage 1 Lire la suite »

novembre 222018

Eastern Works Open House (O’Connor Stop to Kennedy Station)

Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here:

Lire la suite »