Shoring for Caledonia Station

What Work is Taking Place?

Beginning in November 2016, crews will start support of excavation work, also known as shoring, at the future Caledonia Station.  The station is located on the north side of Eglinton Avenue West between Gabian Way and Croham Road (in front of Westside Mall).  Shoring is a common step in the process of constructing the foundation of a building.  Steel piles, as well as braces and tie-backs, will be installed around the perimeter of the station box area to support excavation. Lire la suite »

septembre 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Lire la suite »

juin 242016

Caledonia Station Open House

Thank you for attending our Caledonia station open house on June 23, 2016. 

For those of you who missed it, the presentation is here:

avril 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Lire la suite »

février 012016

Tunnelling: What you may experience

Dear Neighbour:

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Lire la suite »

janvier 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Lire la suite »

janvier 182016

Utility works and geotechnical tests scheduled for the future Caledonia, Dufferin Oakwood, Bathurst and Chaplin LRT Stations

Starting in early January, a work crew will be seen conducting survey, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions near the future LRT Stations for Caledonia, Dufferin, Oakwood, Bathurst and Chaplin. Lire la suite »