WHAT WORK IS TAKING PLACE?

Science Centre Station has advanced to a state to allow the temporary traffic deck to be removed from the roadway. The removal will take place in two stages. The first stage is expected to be complete early May 2020 and will shift to the eastern side of the intersection and continue for approximately two (2) months. The removal of the decking will improve road surface quality.

WORK AREA MAP

HOURS OF WORK

  • Work is expected to begin May 1, 2020 for approximately two (2) months.  
  • Construction works may occur between 7:00 a.m. to 11:00 p.m., Monday to Sunday. 
  • The contractor may not always work during the permitted hours but may do so at its discretion.
  • This traffic change and related construction activities may be delayed or rescheduled due to inclement weather or unforeseen circumstances. 

WHAT TO EXPECT

  • Crews will be removing traffic decking from the intersection using the crane and excavators. 
  • Upon removal of the decking, backfill to the underside of utilities will follow, along with utility restoration.
  • Crews will then backfill to final subgrade.

TRAFFIC IMPACTS

  • North and south traffic will be reduced to two lanes in each direction and aligned to the west side of Don Mills Road.
  • Northbound, southbound and eastbound left turns will be restricted. 

PEDESTRIAN IMPACTS

  • The sidewalk will be open on the north side of Eglinton.
  • The east north-south crosswalk will be closed.
  • The west north-south crosswalk will reopen.
  • Pedestrians will be rerouted around the work zone on the south side of Eglinton Avenue East.

TRANSIT INFORMATION

  • Detours will be required for the 34C and 354 (depicted below).
  • Busses will detour east of Don Mills Road, proceed south on Ferrand Drive, West on Rochefort Drive and then continue north on Don Mills Road.