What's New?
À la recherche de nouvelles concernant des travaux près d’une i
Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.
- Black Creek Drive
- Keele Street
- Caledonia Road
- Dufferin Street
- Oakwood Avenue
- Allen Road
- Bathurst Avenue
- Chaplin Crescent
- Avenue Road
- Yonge Street
- Mount Pleasant Road
- Bayview Avenue
- Donlea Drive/Hanna Road
- Laird Drive
- Leslie Street
- Don Mills Road
- Ferrand Drive
- Wynford Drive
- Bermondsey Road
- Victoria Park Avenue
- Pharmacy Avenue
- Lebovic Avenue
- Warden Avenue
- Birchmount Road
- Ionview Road
- Kennedy Road
- Little Blvd.
- Petman Avenue
- Brentcliffe Road
- Allen Road
- Avenue Road
- Bathurst Avenue
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Lebovic Avenue
- Leslie Street
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Wynford Drive
- Warden Avenue
- Yonge Street
Upcoming Traffic Change and Shoring Update at Chaplin Station
WHAT WORK IS TAKING PLACE?
Chaplin Station construction continues with a variety of ongoing construction activities. Traffic changes are required in order to continue to upgrade existing/install new utilities, continue shoring activities on the north side of Eglinton, and begin shallow excavation on the north side of Eglinton.
The new construction staging and associated traffic changes will be implemented as early as late March 2018. Lire la suite »
Mining at Avenue Station - Both Station Entrances
What Work is Happening?
The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.”
Excavation of the Main Entrance at Avenue Station is nearing completion and mining will begin soon. Lire la suite »
Utilities Relocation and Geotechnical Installations for Fairbank Station - Overnight Work
What Work is Taking Place? Lire la suite »
Toronto Hydro Relocation Work at Cedarvale Station
What Work is Taking Place?
To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating a Toronto hydro infrastructure from underground ducting to overhead cables. The work will involve trenching and removing the existing duct banks, and installing new overhead hydro cables. Lire la suite »
Shoring at Chaplin Station Main Entrance
WHAT WORK IS TAKING PLACE?
Support of excavation (or shoring) continues at Chaplin Station. At the Main Entrance site, located on the northeast corner of Chaplin and Eglinton, there are some piles that remain to be installed.
As early as Wednesday, March 14, crews will begin piling activities at the Main Entrance. The drill will cross Eglinton to the Main Entrance site as early as Monday, March 12.
TIMING Lire la suite »
Equipment Move at Caledonia Station
What Work is Taking Place?
On Monday March 5 and Tuesday March 6, crews will perform maintenance of the water tank at Caledonia Station. The water tank is part of the station’s dewatering system, which removes ground water to make way for excavation. Lire la suite »
OVERNIGHT WORK TO PREPARE FOR WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE
ORIGINAL POST: FEBRUARY, 16, 2018
RE-ISSUE DATE: MARCH 2, 2018
WATERMAIN LINING OVERVIEW Lire la suite »
Mining Equipment Mobilization - 24 Hour Work - Avenue Station Main Entrance
WHAT WORK IS TAKING PLACE?
Mining operations will begin at the Avenue Station Main Entrance in Spring 2018. The mining equipment is planned to be delivered to the site during the weekend of March 2 – 4.
In order to lower the heavy mining equipment to the bottom of the Main Entrance shaft, a temporary crane will be erected on Eglinton Avenue. This crane will take up one additional westbound lane of traffic, just west of Avenue Road. Lire la suite »