Overnight Watermain work for Keelesdale Station

Since December 2015, crews have been conducting work along Eglinton Avenue West in the vicinity of the future Keelesdale Station to prepare for the next phase of construction of the Eglinton Crosstown. Lire la suite »

mai 052016

Keelesdale Station Open House

Thank you for attending our Keelesdale station open house on May 4, 2016. 

For those of you who missed it, the presentation is here:

Lire la suite »

avril 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Lire la suite »

février 012016

Tunnelling: What you may experience

Dear Neighbour:

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Lire la suite »

janvier 282016

Continuing Preparatory Works for the Future Keelesdale Station

Since December 2015, crews have been conducting preparatory activities along Eglinton Avenue West in the vicinity of the future Keelesdale (formerly Keele) Station to prepare for the next phase of construction of the Eglinton Crosstown. Work will continue through winter 2015/2016 in advance of the construction of the Keelesdale Station, which will begin in spring 2016.

What work is starting and where? 

Lire la suite »

janvier 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Lire la suite »

janvier 062016

Preparatory and Early Works Activities Scheduled January-March 2016

Over the next few months, crews will be conducting several activities along the Eglinton Line around the Eglinton Maintenance and Storage facility and the future stations of Keele and Dufferin.

Why: Metrolinx continues to build the Eglinton Crosstown Line (Line). It is now partnering with Crosstown Transit Solutions (CTS) to design and construct the stations and stops, track work, and signaling system. To prepare for construction across the Line, CTS will conduct a number of preparatory and early works activities around each of the underground stations. Lire la suite »

décembre 182015

Tunnelling: What You May Experience

Dear Neighbour:

As you may know, the Eglinton Crosstown is a 19-kilometre light rail transit that includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunneled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel about 10 metres per day. TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Lire la suite »

décembre 182015

Tunnelling: What You May Experience

Dear Neighbour:

As you may know, the Eglinton Crosstown is a 19-kilometre light rail transit that includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunneled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel about 10 metres per day. TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Lire la suite »