Kennedy Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
août 162018

UPDATE: Watermain, Storm and Sanitary Relocation from Ionview Road to Kennedy Road for Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between Ionview Road and Kennedy Road.

Crews continue to work on installing the new storm and sanitary system from Ionview to Kennedy and will complete their work with a final connection to the existing manholes located within the Kennedy and Eglinton intersection. Lire la suite »

août 102018

Ongoing Works at Kennedy Station: Sanitary Sewer Installation at East Service Road

What Work is Taking Place?

As part of the ongoing works to build the future Kennedy Station, crews will be working on the East Service Road installing a new sanitary sewer. This work is expected to begin as early as Friday, August 10 to Friday, August 17, 2018.

Hours of Work Lire la suite »

juillet 202018

Concrete Removal Work at Kennedy Station

What Work is Taking Place?

Kennedy Station will be the terminal station at the eastern end of the Eglinton Crosstown LRT line. Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor- Danforth subway, and a TTC bus terminal. Construction of the future Kennedy Station as part of the Eglinton Crosstown Light Rail Transit (ECLRT) will include upgrades to the existing Kennedy Station infrastructure. Lire la suite »

juillet 202018

Upcoming Traffic Changes at Kennedy and Eglinton In Support of Shoring

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing in late July. Shoring began in April 2018 and will continue in phases at the intersection, taking approximately twelve (12) months to complete. Lire la suite »

juillet 122018

Update: Resumption of Overnight Utility Relocation Work on Transway Crescent for the Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will resume relocating watermain and sanitary utilities on Transway Crescent, starting as soon as July 15, 2018.

To reduce impacts to the community and commuters this work will be performed overnight and will take approximately three (3) weeks to complete.  The work is part of the larger upgrade and relocation of utilities for the Eglinton Crosstown LRT.

Stage 3 Lire la suite »

juillet 062018

Support of Excavation Works at the North End of Kennedy GO Station Platform as Part of Eglinton Crosstown LRT

What Work is Taking Place?

As part of construction of the future Eglinton Crosstown LRT, improvements are also being made to the GO Transit Stouffville Corridor at Kennedy GO Station. Improvements include building a new west platform; rebuilding the existing east platform; constructing a new ticketing building for the GO Station; and building a new south pedestrian underpass. Lire la suite »

juin 272018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committe meeting of Pharmacy to Kennedy was held on June 26, 2018. You can see the presentation here:

juin 132018

UPDATE: Resumption of Overnight Utility Relocation on Transway Crescent and Kennedy Road In Support of Construction of the Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will resume relocating watermain and sanitary utilities on Transway Crescent, starting as soon as June 12, 2018. To reduce impacts to the community and commuters this work will be performed overnight and will take approximately three (3) weeks to complete.  The work is part of the larger upgrade and relocation of utilities for the Eglinton Crosstown LRT.

Stage 1 Lire la suite »

mai 312018

Upcoming Support of Excavation (SOE) at Kennedy Road and Eglinton Avenue East

What Work is Taking Place?

Crews will commence support of excavation (SOE) work, also known as shoring, on the west side of the Kennedy and Eglinton intersection within a protected work zone in June. This work supports construction of the future Kennedy Station. Lire la suite »