novembre 27 2020

Notice of Water Shut-Off at Chaplin Station - November 27, 2020

What Work is Taking Place?

On Friday November 27, 2020, crews will continue water main repair work near Russell Hill Road and Eglinton Avenue and the Chaplin Station Tertiary Entrance.  A water shut-off is required to facilitate the repair.  Water service will be restored upon completion of the work.

Water Shut-off Details:

novembre 22 2020

Sidewalk Construction at Eglinton Square

November 23, 2020

 

What Work is Taking Place?

novembre 17 2020

Laird Station Overnight Backfilling Works - November 18 2020

What Work is Taking Place?

As early as November 18, 2020, crews will begin backfilling activities at the south west corner of Eglinton and Laird Drive. Work will take place between the hours of 9:00p.m. to 5:00 a.m. Monday to Saturday for a period of two (2) weeks.

 

What to Expect

novembre 17 2020

Sidewalk Construction at Eglinton Ave E and Hakimi and Lebovic Ave - East Side

November 18, 2020 for one week

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi and Lebovic Ave intersection. Work on the east side of the intersection is expected to begin November 18, 2020 for a period of one week.

 

novembre 13 2020

North and South Platform Shelter Installation at Sunnybrook Stop

 

November 18, 2020  

       

What Work is Taking Place?

novembre 13 2020

Sidewalk Construction at Eglinton Ave E and Warden Ave - November 16

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Warden Ave intersection. Work on the west side of the intersection is expected to begin as early as November 16, 2020 for a period of one week. Work on the east side of the intersection is expected to begin as early as November 24, 2020 for a period of one week. 

novembre 12 2020

Sidewalk Construction at Eglinton Ave E and Hakimi and Lebovic Ave

 

WHAT WORK IS TAKING PLACE

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi and Lebovic Ave intersection. Work on the west side of the intersection is expected to begin November 12, 2020 for a period of one week. Work on the east side of the intersection is expected to begin November 23, 2020 for a period of one week.

 

novembre 11 2020

Notice of Utility Works at Bayview and Glazebrook Avenues - November 13 2020

Notice of Utility Works at Bayview and Glazebrook Avenues

What Work is Taking Place?


On Friday November 13, 2020, crews at Leaside Station will perform utility works within the left turn lane on Bayview Avenue at Glazebrook Avenue. Work will take place between 10:00 a.m. – 1:00 p.m.

novembre 11 2020

Sidewalk Construction on Eglinton Ave, East of Sloane Avenue

 

What Work is Taking Place?

Crews will be constructing final sidewalks on the north side of Eglinton Avenue East, east of Sloane Avenue. Driveway tie-in works will also be performed at the Eglinton Ave East entrance for the condominiums at 1700, 1720 and 1730 Eglinton Avenue East. Work is expected to begin as early as November 11, 2020 and continue for approximately two weeks.

novembre 05 2020

Sidewalk Construction at Eglinton Ave E and Pharmacy Ave intersection - East Side

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the north-east and south-east corners of the Eglinton Ave E and Pharmacy Ave intersection. Work is expected to begin November 6, 2020 for a period of approximately one week.

 

What to Expect