octobre 25 2017

Avenue Station Construction Updates - October 25

CONSTRUCTION ACTIVITIES AT AVENUE ROAD

Construction activities outside the long-term set up continues to be active as we prepare for upcoming mining operations. These activities are happening during the daytime and nighttime, and overlap. Residents and businesses can expect to see the following daytime and nighttime work at various locations in the roadway or on the sidewalk.

THIS WEEK AT AVENUE STATION: Lire la suite »

octobre 24 2017

Traffic Change at Latimer & Eglinton for Chaplin Station Construction

What Work is Taking Place?

Since spring 2016, crews have been performing utilities relocation and support of excavation (shoring) in the vicinity of Chaplin Crescent and Eglinton Avenue West.  

As early as October 28, 2017, the work zone configuration will change in order to begin shoring and utility work (hydro, sewer) on the north side of Eglinton, while work continues on the south side of Eglinton.  Lire la suite »

octobre 24 2017

Early Morning Concrete Pour at Cedarvale Station for Crossover Track Roof Construction

WHAT WORK IS TAKING PLACE?

  • With the invert concrete slab now complete at the crossover track section east of Cedarvale Station, the next phase is pouring the roof slab. The roof slab will be poured in sections. 
  • Due to the large size of these concrete pours, work will start at 4AM in order to complete the pour during the daytime hours, avoiding late overnight work. 
  • The first pour was successfully completed on October 12.

TIMING Lire la suite »

octobre 24 2017

Allen Road - Short Duration Rolling Lane Reductions - October 27

What Work is Taking Place?

  • Crews need to complete surveying activities for centre lines on Allen Road from Eglinton Avenue West to the Aldburn Road Bridge.
  • For two hours, one in each direction (north and south), Allen Road will have rolling lane reductions.

Timing Lire la suite »

octobre 23 2017

Eglinton Lane Reduction for Cedarvale Station Utility Work

What Work is Taking Place?

  • To accommodate the continued utility works for Cedarvale Station, crews will reduce eastbound Eglinton Avenue from Park Hill Road to Allen Road to one lane to access two maintenance manholes.

Timing

  • The lane reduction is scheduled for October 23 – 27 from 10:00 AM to 3:00 PM daily to reduce impact on peak traffic hours.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

What to Expect

  • Eglinton Avenue will be reduce
octobre 19 2017

Traffic Change at Fairbank Station

What Work is Taking Place?

  • Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West.
  • On October 21, new temporary traffic changes will be implemented at Dufferin Street and Eglinton Avenue West, to make way for support of excavation activity as well as relocation of Bell cables at the northwest and centr
octobre 19 2017

Traffic Change at Fairbank Station - October 2017

What Work is Taking Place?

Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West. Lire la suite »

octobre 18 2017

Preparing to Realign Allen Road South

PREPARING TO REALIGN ALLEN ROAD SOUTH

In early 2018, the construction work zones and traffic set up will change again for the next phase of support of excavation (shoring) activities on the north side of Eglinton Avenue West at Allen Road.

This requires the Allen Road South off-ramp to be realigned approximately 20m west.

The existing All Road South off-ramp will be in place as-is until early 2018.


What Work is Taking Place? Lire la suite »

octobre 18 2017

Avenue Construction Updates - October 18

Construction Activities at Avenue Road and Eglinton

As we gear up to begin mining operations at the Secondary Entrance in November, there are many other parcels of preparatory work to complete. Construction outside of the long-term set up is very active and will be for the rest of the year.

Residents and businesses can expect to see many works happening at various locations in the roadway or on the sidewalk, often at the same time.

  Lire la suite »

octobre 12 2017

Sewer Lining Activities at Avenue Station - Bypass Installation & Lining Operations

SEWER LINING AT AVENUE STATION

The entire sewer lining process will take approximately 4 – 6 weeks to complete.

Sewer bypass work takes place in the daytime construction hours.

Sewer lining work takes place on a 24 hour schedule.

WHAT WORK IS TAKING PLACE? Lire la suite »