What's New?

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

 
Syndicate content
 
octobre 24 2017

Early Morning Concrete Pour at Cedarvale Station for Crossover Track Roof Construction

WHAT WORK IS TAKING PLACE?

  • With the invert concrete slab now complete at the crossover track section east of Cedarvale Station, the next phase is pouring the roof slab. The roof slab will be poured in sections. 
  • Due to the large size of these concrete pours, work will start at 4AM in order to complete the pour during the daytime hours, avoiding late overnight work. 
  • The first pour was successfully completed on October 12.

TIMING Lire la suite »

octobre 23 2017

Eglinton Lane Reduction for Cedarvale Station Utility Work

What Work is Taking Place?

  • To accommodate the continued utility works for Cedarvale Station, crews will reduce eastbound Eglinton Avenue from Park Hill Road to Allen Road to one lane to access two maintenance manholes.

Timing

  • The lane reduction is scheduled for October 23 – 27 from 10:00 AM to 3:00 PM daily to reduce impact on peak traffic hours.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

What to Expect

  • Eglinton Avenue will be reduce
octobre 19 2017

Traffic Change at Fairbank Station - October 2017

What Work is Taking Place?

Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West. Lire la suite »

octobre 19 2017

Traffic Change at Fairbank Station

What Work is Taking Place?

  • Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West.
  • On October 21, new temporary traffic changes will be implemented at Dufferin Street and Eglinton Avenue West, to make way for support of excavation activity as well as relocation of Bell cables at the northwest and centr
octobre 18 2017

Avenue Construction Updates - October 18

Construction Activities at Avenue Road and Eglinton

As we gear up to begin mining operations at the Secondary Entrance in November, there are many other parcels of preparatory work to complete. Construction outside of the long-term set up is very active and will be for the rest of the year.

Residents and businesses can expect to see many works happening at various locations in the roadway or on the sidewalk, often at the same time.

  Lire la suite »

octobre 18 2017

Preparing to Realign Allen Road South

PREPARING TO REALIGN ALLEN ROAD SOUTH

In early 2018, the construction work zones and traffic set up will change again for the next phase of support of excavation (shoring) activities on the north side of Eglinton Avenue West at Allen Road.

This requires the Allen Road South off-ramp to be realigned approximately 20m west.

The existing All Road South off-ramp will be in place as-is until early 2018.


What Work is Taking Place? Lire la suite »

octobre 12 2017

Sewer Lining Activities at Avenue Station - Bypass Installation & Lining Operations

SEWER LINING AT AVENUE STATION

The entire sewer lining process will take approximately 4 – 6 weeks to complete.

Sewer bypass work takes place in the daytime construction hours.

Sewer lining work takes place on a 24 hour schedule.

WHAT WORK IS TAKING PLACE? Lire la suite »

octobre 12 2017

Early Morning Equipment Move and Deliveries at Chaplin Station

What Work is Taking Place?

On Friday October 13, crews will move heavy equipment from the southwest work zone eastward along Eglinton Avenue to the southeast work zone.

On Tuesday October 17, crews will receive a large delivery of steel beams to be hoisted from Eglinton Avenue into the work zone.  Lire la suite »

octobre 10 2017

Mining at Avenue Station

Mining is expected to begin in November 2017, and will carry on through to late 2019.

What Work is Happening?

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.” 

Excavation of the entrances at Avenue Station is nearing completion and mining will begin soon. Lire la suite »

octobre 06 2017

Overnight and Early Morning Works at Cedarvale Station for Roof Slab Concrete Pour and Traffic Deck Coating

What Work is Taking Place?

 

  • Next week, two nights of overnight work are required and one early morning concrete pour is planned.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Traffic Deck Coating

TUESDAY OCTOBER 10 at 7PM – WEDNESDAY OCTOBER 11 at 5AM

WEDNESDAY OCTOBER 11 at 7PM – THURSDAY OCTOBER 12 at 5AM

  Lire la suite »