mars 24 2016
février 24 2016

Demolition Work for Future Laird Station

What work is starting?

In February 2016, crews began conducting preparatory activities and utilities works including surveying, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions in the Laird Avenue and Eglinton Avenue East vicinity to make way for the future Laird Station.

Upcoming Works – Demolition Lire la suite »

janvier 08 2016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

What: To prepare for west headwall construction for the future Bayview Station, crews are rehabilitating and upgrading an existing underground sewer on Eglinton Avenue East between east of Banff Road and west of Bayview Avenue. 

When: Work began in December, 2015, and will continue for several weeks. Work may be rescheduled or adjusted due to weather conditions or unforeseen circumstances.

Please be advised:  Lire la suite »

mai 14 2015

Temporary Water Shut Off - Wednesday May 20th 2015

What:  A temporary Water Shut Off is scheduled for the above noted date. During this time, the water main will be shut off and there will be no water available from the taps. 

When:  10:00 am to 5:00 pm on, Wednesday May 20th, 2015 

Where:  Temporary water shut off will be experienced by north side properties of:

1220 to 1164 Eglinton Ave West Lire la suite »

mai 08 2015

Temporary Water Shut Off - Saturday, May 9, 2015

What:  There will be a temporary water shut off on Saturday, May 9th. Between 6:00am and 9:00am, there will be no water available from the taps.  

When:  Saturday, May 9, 2015, 6:00 A.M. to 9:00 A.M.

Where:  Temporary water shut off will be experienced at the following addresses:

  • 20, 30, 40, 50 Eglinton Avenue East (north side)

Why:  Construction on the water main is part of the continued construction of the extraction shaft.  Lire la suite »

avril 27 2015

Cross Passage Headwall Construction near Duncannon Drive Continues - Stage 2

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels required for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels.  Lire la suite »

avril 22 2015

Three Hour Parking – Tarlton Road Eglinton Avenue West to College View Avenue

What:  Maximum 3 hour parking will be allowed on Tarlton Road for the duration of this phase of construction on Eglinton Avenue.

Why:  On-street parking will not be available within the vicinity of construction along Eglinton Avenue between Bathurst Street and Avenue Road. To alleviate the loss of parking on Eglinton Avenue during construction, the City of Toronto, in collaboration with Metrolinx, will be adjusting the parking restrictions in certain sections to accommodate parking for the neighbourhood and businesses.     Lire la suite »

avril 17 2015

Assistez au déplacement de nos tunneliers!

Le 18 avril 2015

Chers amis et voisins,

Soyez des nôtres ce samedi 18 et ce dimanche 19 avril pour assister à une étape importante du projet de transport léger sur rail (TLR) Eglinton Crosstown! 

Dennis et Lea, les tunneliers qui ont creusé le tronçon ouest de la partie souterraine de la ligne Crosstown, seront hissés du puits d’extraction à l’ouest d’Allen Road et seront transportés jusqu’au puits de lancement situé à l’est d’Allen Road.

TBM lift photo Lire la suite »

janvier 08 2015

Retour sur l’année 2014

Le projet Eglinton Crosstown est une ligne de transport léger sur rail (TLR) de 19 kilomètres qui longera Eglinton Avenue au cœur de Toronto et comprendra un tunnel souterrain de 10 kilomètres dans sa section centrale. Lorsqu’elle sera terminée, la ligne reliera Mount Dennis, à l’ouest, à Kennedy Road, à l’est, et offrira un service jusqu’à 60 % plus rapide que le service d’autobus actuel.  Lire la suite »

décembre 05 2014

Utility Relocation Work near Yonge Street for Extraction Shaft - Temporary Closure of Holly Street

What we are building

What: Crews are working on advanced utility construction and relocation prior to the building of support headwalls and an extraction shaft, located within the Eglinton Avenue roadway on the east side of Yonge Street.  Lire la suite »