Keelesdale Station Traffic Reconfiguration - Thursday December 22, 2016 (overnight)

What Work is Taking Place?

As part of the continued traffic staging set up at Keele Street/Trethewey Drive and Eglinton Avenue West for support of excavation works for the Keelesdale Station traffic restrictions in this area is changing. Lire la suite »

novembre 08 2016

UPDATED: Overnight Line Painting for Science Centre Station Starts Friday, November 11, 2016

UPDATED
Overnight lane reductions on Don Mills Road and on Eglinton Avenue East will be required begining on Friday, November 11 for approximatley 3 nights as crews remove existing line markings on the roadway then repaint in preparation for station construction at the future Science Centre Station. 

What to Expect Lire la suite »

octobre 20 2016

Telecom Relocation for Leaside Station

What Work is Taking Place?

Crews will relocate existing telecommunications utilities from overhead to underground around the Eglinton Avenue and Bayview Avenue intersection. For the safety of the public and workers, temporary pedestrian and traffic changes will be in effect to accommodate this work. Lire la suite »

mai 27 2016

Mount Pleasant Installation of Dewatering Wells June 2016

What work is starting?

What: Crews are required to install dewatering wells in advance of the arrival of the tunnel boring machines, Don and Humber. Following the installation, dewatering work will commence as early as late June 2016.

When: Starting as early as May 30, 2016 until late June 2016, construction will begin on the south side of Eglinton Avenue East, east of Mount Pleasant Road. Some work may be rescheduled or adjusted due to weather conditions and/or unforeseen circumstances. Lire la suite »

mars 24 2016
février 24 2016

Demolition Work for Future Laird Station

What work is starting?

In February 2016, crews began conducting preparatory activities and utilities works including surveying, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions in the Laird Avenue and Eglinton Avenue East vicinity to make way for the future Laird Station.

Upcoming Works – Demolition Lire la suite »

janvier 08 2016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

What: To prepare for west headwall construction for the future Bayview Station, crews are rehabilitating and upgrading an existing underground sewer on Eglinton Avenue East between east of Banff Road and west of Bayview Avenue. 

When: Work began in December, 2015, and will continue for several weeks. Work may be rescheduled or adjusted due to weather conditions or unforeseen circumstances.

Please be advised:  Lire la suite »