Mount Pleasant Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
mars 192021

Temporary Crane at Mt Pleasant Station’s Main Entrance

 

Traffic Configuration

 

A mobile crane is currently being used at Mt Pleasant Station’s Main Entrance site to assist with lifting operations in and out of the station box. The crane will be stationed at the Main Entrance for approximately three (3) weeks. Crane operations will take place within the work zone only. 

 

What to Expect

  Lire la suite »

mars 162021

Overnight Work at Mt Pleasant Station’s Secondary Entrance - March 16, 2021

 

Traffic Configuration

 

On Tuesday, March 16, 2021, crews at Mount Pleasant Station will work overnight to remove soil from the Secondary Entrance site. This work will take place between 7:00 p.m. – 6:00 a.m. for one (1) night. 

 

Use of a crane and excavator will be required to complete this work. To minimize disruption, hauling activities will be reserved for the next day of work. 

 

What to Expect

  Lire la suite »

mars 102021

Mount Pleasant Station Overnight Pile Removals: Stage 1 - March 15, 2021

Traffic Configuration

 

As early as Monday, March 15, 2021, crews at Mount Pleasant Station will work overnight to cut steel supports (piles) from the station roof. Work will take place on the north side of Eglinton Avenue, east and west of Mt Pleasant Road. Once the piles are cut, the sidewalks on the north side of Eglinton Avenue will be backfilled and paved.   Lire la suite »

janvier 272021

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - Jan 30, 2021

Traffic Configuratoin

As early as Saturday January 30, 2021 crews at Mount Pleasant Station will perform a major concrete pour within the work zones on the north side of Eglinton Avenue East, east of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 6:00 a.m. and take approximately 12 hours to complete.

  Lire la suite »

janvier 192021

Eglinton - Mount Pleasant CLC 13 Jan 2021

Construction Updates for Eglinton Station and Mount Pleasant Station. 

 

 

 

Lire la suite »