Overnight Utility Work at Mount Pleasant Station - February 18 to 20, 2020

What Work is Taking Place?

From Tuesday February 18 to Thursday February 20, 2020, crews will work overnight to connect a temporary power line to the main entrance of Mount Pleasant Station. Work will take place within the work zones, however some overnight work in live traffic is required.  Lire la suite »

février 052020

UPDATED: Weekend Lane Reduction at Mount Pleasant and Eglinton - Saturday February 15 – Sunday February 16, 2020

 

What Work is Taking Place?

From Saturday February 15 – Sunday February 16, 2020 crews will install geotechnical monitoring equipment within the eastbound lane on Eglinton Avenue East.  Lire la suite »

janvier 312020

Upcoming Concrete Pour at Mount Pleasant Station Wednesday, February 5, 2020

 

What Work is Taking Place?

As early as Wednesday, February 5, 2020, crews will perform a concrete pour in the north work zone at Mount Pleasant Road and Eglinton Avenue East.  The concrete will form part of the roof of Mount Pleasant Station. Two concrete pumps will be set up within the work zone. Lire la suite »

janvier 282020

Upcoming Concrete Pour at Mount Pleasant Station - Saturday, February 1, 2020

 

What Work is Taking Place?

As early as Saturday February 1, 2020, crews will perform a concrete pour in the northeast work zone at Mount Pleasant Road and Eglinton Avenue East.  The concrete will form part of the roof of Mount Pleasant Station. Two concrete pumps will be set up within the work zone. Lire la suite »

janvier 222020

Temporary Driveway Restrictions at Mount Pleasant Station - Tuesday, January 28, 2020

 

What Work is Taking Place?

On Tuesday, January 28, 2020, crews will perform geotechnical monitoring work to support the construction of Mount Pleasant Station. As part of this work, crews will need to stage a hydro-vac truck in front of the driveway on the west side of Mount Pleasant Road, north of Eglinton Avenue East.

In order to safely and promptly carry out this work, there will be temporary driveway access restrictions as geotechnical monitoring installation takes place.  Lire la suite »

janvier 092020

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant was held on January 8, 2020. You can view the presentation here:

 

Lire la suite »

janvier 092020

Reminder: Extended Construction Hours at Mount Pleasant Station Continues through to February 2020

Reminder: Extended Construction Hours at Mount Pleasant Station Continues through to February 2020 Lire la suite »