Mount Pleasant Road
À la recherche de nouvelles concernant des travaux près d’une i
Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.
- Black Creek Drive
- Keele Street
- Caledonia Road
- Dufferin Street
- Oakwood Avenue
- Allen Road
- Bathurst Avenue
- Chaplin Crescent
- Avenue Road
- Yonge Street
- Mount Pleasant Road
- Bayview Avenue
- Donlea Drive/Hanna Road
- Laird Drive
- Leslie Street
- Don Mills Road
- Ferrand Drive
- Wynford Drive
- Bermondsey Road
- Victoria Park Avenue
- Pharmacy Avenue
- Lebovic Avenue
- Warden Avenue
- Birchmount Road
- Ionview Road
- Kennedy Road
- Little Blvd.
- Petman Avenue
- Brentcliffe Road
- Allen Road
- Avenue Road
- Bathurst Avenue
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Lebovic Avenue
- Leslie Street
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Wynford Drive
- Warden Avenue
- Yonge Street

Temporary Crane at Mt Pleasant Station’s Main Entrance
A mobile crane is currently being used at Mt Pleasant Station’s Main Entrance site to assist with lifting operations in and out of the station box. The crane will be stationed at the Main Entrance for approximately three (3) weeks. Crane operations will take place within the work zone only.
What to Expect
Overnight Work at Mt Pleasant Station’s Secondary Entrance - March 16, 2021
On Tuesday, March 16, 2021, crews at Mount Pleasant Station will work overnight to remove soil from the Secondary Entrance site. This work will take place between 7:00 p.m. – 6:00 a.m. for one (1) night.
Use of a crane and excavator will be required to complete this work. To minimize disruption, hauling activities will be reserved for the next day of work.
What to Expect
Mount Pleasant Station Overnight Pile Removals: Stage 1 - March 15, 2021
As early as Monday, March 15, 2021, crews at Mount Pleasant Station will work overnight to cut steel supports (piles) from the station roof. Work will take place on the north side of Eglinton Avenue, east and west of Mt Pleasant Road. Once the piles are cut, the sidewalks on the north side of Eglinton Avenue will be backfilled and paved. Lire la suite »
Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - Jan 30, 2021
As early as Saturday January 30, 2021 crews at Mount Pleasant Station will perform a major concrete pour within the work zones on the north side of Eglinton Avenue East, east of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 6:00 a.m. and take approximately 12 hours to complete.
Construction Notice: Upcoming Concrete Pour at Mount Pleasant and Eglinton Ave E - December 30, 2020
What Work is Taking Place? Lire la suite »