Toronto Hydro Relocation Work at Cedarvale Station

What Work is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating a Toronto hydro infrastructure from underground ducting to overhead cables. The work will involve trenching and removing the existing duct banks, and installing new overhead hydro cables. Lire la suite »

mars 12 2018

Shoring at Chaplin Station Main Entrance

WHAT WORK IS TAKING PLACE?

Support of excavation (or shoring) continues at Chaplin Station. At the Main Entrance site, located on the northeast corner of Chaplin and Eglinton, there are some piles that remain to be installed.

As early as Wednesday, March 14, crews will begin piling activities at the Main Entrance. The drill will cross Eglinton to the Main Entrance site as early as Monday, March 12.

TIMING  Lire la suite »

mars 08 2018
mars 05 2018

Equipment Move at Caledonia Station

What Work is Taking Place?

On Monday March 5 and Tuesday March 6, crews will perform maintenance of the water tank at Caledonia Station. The water tank is part of the station’s dewatering system, which removes ground water to make way for excavation.  Lire la suite »

mars 02 2018

OVERNIGHT WORK TO PREPARE FOR WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE

ORIGINAL POST: FEBRUARY, 16, 2018

RE-ISSUE DATE: MARCH 2, 2018

WATERMAIN LINING OVERVIEW Lire la suite »

février 23 2018

Mining Equipment Mobilization - 24 Hour Work - Avenue Station Main Entrance

WHAT WORK IS TAKING PLACE?

Mining operations will begin at the Avenue Station Main Entrance in Spring 2018. The mining equipment is planned to be delivered to the site during the weekend of March 2 – 4. 

In order to lower the heavy mining equipment to the bottom of the Main Entrance shaft, a temporary crane will be erected on Eglinton Avenue. This crane will take up one additional westbound lane of traffic, just west of Avenue Road. Lire la suite »

février 20 2018

REPOST & UPDATE: Avenue Station Sewer Lining - East Sewer Section

Original Issue Date: October 14, 2017 (West Sewer Section info)
Updated: January 23, 2018 (East Sewer Section - timing update) 
Updated: February 16, 2018 (East Sewer Section info and timing)
Updated: February 20, 2018 (East Sewer Section - timing update)  Lire la suite »