Temporary Lane Restriction on Eglinton Avenue East at Bayview Avenue January 13, 2020

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

 
janvier 10, 2020

Temporary Lane Restriction on Eglinton Avenue East at Bayview Avenue  

January 13, 2020


What Work is Taking Place?

As work progresses at Leaside station, crews will be installing additional geotechnical monitoring equipment at the south east corner of the intersection on Monday, January 13, 2020. To complete the work safely a temporary closure one eastbound curb lane on Eglinton Avenue East will be required starting at 9:00 a.m. for approximately six (6) hours.

Hours of Work

  • Starting as early as 9:00 a.m. on January 13, 2020 for approximately six hours.
  • Work may occur between the hours of 7:00 AM and 11:00 PM, seven (7) days a week.
  • The contractor may not always work during the permitted hours but may do so at its discretion. Work may be rescheduled due to weather conditions or unforeseen circumstances.

Work Area Map

What to Expect

  • Temporary lane closure of one eastbound curb lane on Eglinton Avenue East, east of Bayview Ave. Trucks and pumps will be staged within the closure.
  • Crews will be installing geotechnical monitoring equipment on the south east corner of the intersection.
  • Noise from equipment and trucks can be expected.
  • Pedestrians and road users can expect delays when travelling through the work zone. 

Traffic Details

  • Temporary lane closure of one eastbound curb lane on Eglinton Avenue East, east of Bayview Ave.
  • A minimum of one through lane of traffic in each direction will be maintained. 

Transit Information

  • There will be no impacts to existing TTC stops.
  • Visit www.ttc.ca for more information.

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

Disponible en français

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.