WHAT WORK IS TAKING PLACE?

In late January, piling on the north side of Eglinton Avenue West will be complete and crews will move to the south side of Eglinton Avenue West to begin support of excavation activities, including piling, shallow excavation and roof slab construction.  This work will take place in several stages over a period of approximately eight (8) months.  In late 2018, crews will return to the north side of Eglinton Ave W to complete shallow excavation and roof slab construction.

As early as February 3 2018 a new traffic stage will be implemented at Dufferin Street and Eglinton Avenue West.  Significant traffic and pedestrian changes will be in effect.  Traffic on Eglinton Ave W will be shifted to the north. 

UPCOMING CONSTRUCTION STAGING


TIMING 
  • As early as February 3, 2018 
  • Permitted hours are 7:00 a.m. to 11:00 p.m., Monday through Sunday
WHAT TO EXPECT
  • Significant traffic and pedestrian changes will be in effect.
  • Fencing, scaffolding, dust cloth will be erected around work zones and pedestrian paths.
  • Noise from construction activity as well as site lighting can be expected.
  • Pedestrians and road users can expect delays when travelling through the intersection.
TRAFFIC AND PEDESTRIAN IMPACTS
  • Traffic on Eglinton Ave W will be shifted to the north.
  • The southeast pedestrian rerouting will remain in effect.
  • TTC bus stops may be relocated away from construction zones.
  • On-street parking may be temporarily eliminated to accommodate construction – three (3) hour on-street parking is available on Livingstone Ave (one street north of Eglinton Ave)

STAY INFORMED

  • Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

PLEASE CONTACT US

  • If you would like more detail about this work or any other aspect of the Eglinton Crosstown project, please contact the west community office at (416) 782-8118.