Traffic Change at Fairbank Station

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

 
mars 27, 2018

WHAT WORK IS TAKING PLACE?

On Wednesday, March 28, 2018, crews will implement a new traffic stage at Eglinton Avenue West and Dufferin Street for work related to support of excavation and utilities relocations, including shallow excavation at the Main Entrance, pile installation and Bell relocation in the roadway.

CONSTRUCTION STAGING

Beginning as early as March 28, 2018 for four (4) weeks.

TIMING

Permitted hours are 7:00 a.m. to 11:00 p.m., seven (7) days per week

WHAT TO EXPECT

  • Noise from construction activity as well as site lighting can be expected
  • Fencing, scaffolding, dust cloth may be erected around work zones
  • Pedestrians and road users can expect delays when travelling through the intersection

TRAFFIC AND PEDESTRIAN IMPACTS

  • Traffic lanes on Dufferin Street will shift to the east during this stage
  • The west crosswalk will close and the east crosswalk will be reinstated