Victoria Park Avenue
À la recherche de nouvelles concernant des travaux près d’une i
Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.
- Black Creek Drive
- Keele Street
- Caledonia Road
- Dufferin Street
- Oakwood Avenue
- Allen Road
- Bathurst Avenue
- Chaplin Crescent
- Avenue Road
- Yonge Street
- Mount Pleasant Road
- Bayview Avenue
- Donlea Drive/Hanna Road
- Laird Drive
- Leslie Street
- Don Mills Road
- Ferrand Drive
- Wynford Drive
- Bermondsey Road
- Victoria Park Avenue
- Pharmacy Avenue
- Lebovic Avenue
- Warden Avenue
- Birchmount Road
- Ionview Road
- Kennedy Road
- Little Blvd.
- Petman Avenue
- Brentcliffe Road
- Allen Road
- Avenue Road
- Bathurst Avenue
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Lebovic Avenue
- Leslie Street
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Wynford Drive
- Warden Avenue
- Yonge Street

New Traffic Configuration: Eglinton Avenue East at Jonesville Crescent
WHAT WORK IS TAKING PLACE?
As utility installations progress along Eglinton Avenue East between Bermondsey Road and Victoria Park Avenue, four (4) new traffic stages will be implemented at Jonesville Crescent to accommodate the work zones (depicted below). Traffic will shift to the first stage as early as Monday, March 4th, 2019. Each stage will last approximately one (1) week. Lire la suite »
Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Lire la suite »
East At-Grade Town Hall Meeting
Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:
Overnight Temporary Traffic Diversion to Facilitate Sub-Surface Infrastructure for Future Traffic Signals at Eglinton Square
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be installing the conduits for the permanent traffic signals at Eglinton Square. Starting as early as Wednesday, February 20, 2019 until Thursday, February 21, 2019. The work will taking place during the overnight period. Lire la suite »
Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Lire la suite »
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Pharmacy to Kennedy was held on January 29, 2019. You can see the presentation here:
Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.
Telecom work has been extended until the Spring 2019.
New Traffic Configuration: Eglinton Avenue East between Sloane Avenue and Victoria Park Avenue
Last Updated: January 14, 2019
WHAT WORK IS TAKING PLACE?
As part of utility relocations, road widening and road reconstruction along Eglinton Avenue East between Sloane Avenue and Victoria Park Avenue, new traffic staging (depicted below) will be implemented as early as January 15, 2019. This traffic configuration will be in place for up to four (4) weeks.
All works are in support of the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East. Lire la suite »
Watermain Upgrade at Victoria Park and Eglinton Avenue East Intersection
Last Updated: January 11, 2019
WHAT WORK IS TAKING PLACE?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be upgrading the existing watermains at Victoria Park Ave crossing the Eglinton LRT guideway. This work requires digging a trench to access and upgrade the existing watermain as well as installing new control valves. Lire la suite »
Eastern Works Open House (O’Connor Stop to Kennedy Station)
Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here: