mai 152019

Concrete Pour of Guideway - East of Warden Avenue May 16 and May 17, 2019

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East, just east of Warden Avenue and Thermos/Sinnott Road. Lire la suite »

mai 132019

Construction Begins for Traction Power Substation 11

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be commencing construction of the Traction Power Substation (TPSS) 11 that will power the Eglinton Crosstown Light Rail Transit (ECLRT). The work will take place in the work zone on the south east side of Warden Avenue in close proximity to 795 Warden Avenue Lire la suite »

mai 102019

Track Slab Concrete Pour of Guideway- Eglinton Square

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. 

Crews will be delivering and pouring cement along Eglinton Avenue East between Eglinton Square and Pharmacy Avenue as early as Wednesday May 15 from 7:00 a.m. until 7:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west of Eglinton Avenue East. Lire la suite »

avril 302019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on April 30, 2019. You can see the presentation here:

Lire la suite »

avril 182019

Updated: Concrete Pour of Guideway - East of Warden Avenue - April 22 & April 24, 2019

Originally Posted: April 15, 2019

Updated: April 18, 2019 

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East, just east of Warden Avenue and Thermos/Sinnott Road. Lire la suite »

avril 112019

Eastern Works Open House

Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here:

Download the presentation

avril 112019

Updated: Guideway Work along Surface Section of the Eglinton Crosstown LRT: Thermos Road/Sinnott Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East between Warden Avenue and Birchmount Road. Preliminary work began on March 16, 2019. Lire la suite »

avril 092019

Concrete Pour of Guideway- Warden Avenue- April 10, 2019

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East just east of Warden Avenue and Thermos/Sinnott Road. Lire la suite »

mars 262019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on March 26, 2019. You can see the presentation here:

Lire la suite »

mars 132019

Updated: Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as March 16, 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.  Lire la suite »