Yonge Street

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
juin 102021

TTC Line 1 Closure for Eglinton Crosstown LRT Construction Work

Traffic Configuration

 

TTC’s Line 1 subway will be closed between Finch and St. Clair stations on Saturday, June 12 and Sunday, June 13, 2021, while crews perform TTC platform relocation and associated track level works. Work will take place on a 24-hour basis on Saturday, June 12 and Sunday, June 13, 2021. Berwick Avenue will remain open while this work takes place.

 

What to Expect

  Lire la suite »

mai 202021

Upcoming Concrete Pour at Eglinton Avenue and Yonge Street

 

Traffic Configuration

 

As early as Saturday, May 22, 2021 crews at Eglinton Station will perform a concrete pour on the north side of Eglinton Avenue, east of Cowbell Lane. The concrete will form one of the permanent underground station structures. To ensure the integrity and continuity of the pour, work will begin as early as 4:00 a.m. and take approximately twelve (12) hours to complete.

  Lire la suite »

mai 072021

TTC Line 1 Closure for Eglinton Crosstown LRT Construction Work

 

Traffic Configuration

TTC’s Line 1 subway will be closed between Lawrence and St. Clair stations on Saturday, May 8 and Sunday, May 9, 2021, while crews perform TTC platform relocation and associated track level works. Work will take place on a 24-hour basis on Saturday, May 8 and Sunday, May 9, 2021. Berwick Avenue will remain open during this work.

 

What to Expect

  Lire la suite »

mai 052021

Lane Shift on Yonge Street for Wet Utility Relocation Works

Traffic Configuration

As early as Friday, May 7, 2021, traffic lanes on Yonge Street south of Eglinton Avenue will shift to the east side of the street to allow space for a temporary work zone on the west side of the street. Within the work zone, crews will perform wet utility relocation works for Eglinton Station’s South East Entrance. The temporary work zone will remain in place for approximately three (3) weeks. 

  Lire la suite »

mai 052021

Central East Crosstown Virtual Open House Presentation

Construction and progress updates for stations and stop including: Eglinton, Mount Pleasant, Leaside, Laird, Sunnybrook Park and Science Centre.

Lire la suite »

avril 232021

TTC Line 1 Closure for Eglinton Crosstown LRT Construction Work

Traffic Configuration

 

TTC’s Line 1 subway will be closed between Finch and St. Clair stations on Saturday April 24 and Sunday April 25, 2021, while crews perform TTC platform relocation and associated track level works. Work will take place on a 24-hour basis on Saturday April 24 and Sunday April 25, 2021. Berwick Avenue will remain open while this work takes place.

 

What to Expect

  Lire la suite »

avril 062021

Update: Crane Mobilization on Berwick Avenue

Traffic Configuration

 

As early as Friday April 9, 2021, crews at Eglinton Station will resume pre-cast panel installations at the Berwick Portal site. To facilitate this work, use of a mobile crane will be required at the Berwick Portal until approximately Friday, April 16, 2021. 

  Lire la suite »