Overnight Road Closures for Tunnel Boring Machine Removal - March – April 2020

 

What Work is Taking Place?

Starting Tuesday March 10, 2020, crews at Eglinton LRT Station will begin removing the tunnel boring machines (TBMs) from the excavation on the northeast corner of Duplex Avenue and Eglinton Avenue West. The TBMs will be removed in six heavy loads, followed by approximately 25 smaller loads. The six heavy loads will be removed using a crane that will place each load onto a truck to be taken to an off-site facility.   Lire la suite »

mars 042020

Spring Open House: Central West - March 3, 2020

Thank you for attending the Central West Open House on March 3, 2020. For those who weren't able to make it out in person, the presentation is here:

Lire la suite »

février 102020

TTC Bus Rerouting at Eglinton Station: Late March to Late Summer 2020

What Work is Taking Place?

In late March 2020, the bus loop at Eglinton West Station, located at Allen Road and Eglinton Avenue, will be closed for approximately five (5) months while crews construct a roof for the future Cedarvale LRT Station. During the closure, the 32D Eglinton West bus will extend to Eglinton Station.  Lire la suite »

janvier 132020

Line 1 Subway Closure and Berwick Avenue Road Closure for TTC Line 1 Facility Service Building Construction - Friday January 17 – 20, 2020

 

 

What Work is Taking Place?

Construction of a new Facility Service Building for TTC’s Line 1 Subway is underway at Berwick Avenue and Yonge Street.  Some of the work can only be safely performed while the subway is not operational.  Crews will work Friday January 17 through Monday January 20, 2020, to perform plumbing work at the Berwick Ave site, maintenance north of the platform track and to install additional hoarding on the platform for elevator construction.  

  Lire la suite »

janvier 092020

UPDATE: Deep Excavation Works at Eglinton Station

Updated: January 9, 2020

Original Post: December 6, 2018

 

What Work is Taking Place?

Deep excavation work will continue to prepare for station construction through 2020. This work will include excavating to the bottom of the future station box (approximately 22 meters at the deepest point). Spoils from the excavation will be extracted and hauled from the existing TTC bus depot site at the southeast corner of Duplex Avenue and Eglinton Avenue West, and the Salvation Army site at the corner of Eglinton Avenue East and Cowbell Lane. Lire la suite »

janvier 092020

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant was held on January 8, 2020. You can view the presentation here:

 

Lire la suite »

décembre 092019

Lane Shift on Yonge Street for Utility Investigation Work - December 2019

 

As early as December 9, 2019, lanes on Yonge Street between Roehampton Avenue and Eglinton Avenue will be shifted to the west side of the street to make way for a temporary work zone on the east side of the street in order to perform an utility investigation for the ongoing tunnel ventilation shaft construction. The temporary work zone will remain in place until the end of December 2019.  No changes for pedestrian routes are required.  All four crosswalks at Yonge Street and Eglinton Avenue will remain open.

  Lire la suite »

novembre 272019

Update: Cross Passage 10 at Lillian Street

Original Post: November 5, 2019

Updated on November 27, 2019

Underground excavation continues in the tunnels below Eglinton Avenue East at Lillian Street. This work occurs on a 24- hour basis and is expected to be completed by February 2020. The excavation will create a connection corridor underground between the north tunnel and the south tunnel.

The dewatering system located on the southeast corner of Lillian Street that has been operating on a 24-hour basis since early 2019, will continue to operate on the surface until excavation is complete. Lire la suite »