Shoring for Caledonia Station

 
novembre 21, 2016

What Work is Taking Place?

Beginning in November 2016, crews will start support of excavation work, also known as shoring, at the future Caledonia Station.  The station is located on the north side of Eglinton Avenue West between Gabian Way and Croham Road (in front of Westside Mall).  Shoring is a common step in the process of constructing the foundation of a building.  Steel piles, as well as braces and tie-backs, will be installed around the perimeter of the station box area to support excavation. This stage will take approximately sixteen (16) weeks to complete.

Hours of Work

  • This work will be conducted Monday through Friday between the hours of 7:00 AM and 11:00 PM, with crews working until 11:00 PM on a regular basis
  • The contractor may not always work during the permitted hours, but may do so at its discretion
  • In the event that overnight work is required, Metrolinx and CTS will notify the public in advance and monitor activities throughout
  • Work is subject to permits and all relevant approvals, and may be rescheduled due to weather or unforeseen circumstances

Caledonia Shoring Works

What to Expect

  • Nearby residents and businesses can expect increased noise in the area caused by a pile drill, crane, loaders, trucks and other construction equipment
  • Dust from drilling activity and debris removal can be expected
  • Truck traffic entering and exiting the work zone can be expected
  • In addition to construction activity, residents can expect to see equipment and material storage within the work zone
  • For safety purposes, metal fencing has been erected around the work zone

Pedestrian Details

  • Pedestrian access will be maintained
  • The existing pedestrian rerouting around the work zone onto Eglinton Avenue West will remain in effect

Traffic Details

  • Truck traffic will enter and exit site from Eglinton Avenue West at  the south and south east sides of the work zone  
  • Motorists may experience delays while trucks enter and exit the work zone
  • A flag person will be present to direct truck and pedestrian traffic
  • As always, please take care when travelling near construction zones

For more information about the permits associated with this road closure please see here

Contact Us

For more information about this work, please contact Carlos Hernandez at 416-782-8118 or

crosstown@metrolinx.com.

 

Thank you for your patience as we work to build this important project

Please support your local businesses during construction.