UPDATE: Traffic reconfiguration in support of excavation works and utility relocations beginning February 17 for Science Centre Station

 
février 7, 2017

What Work is Taking Place?

As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing as early as February 17, 2017.

Weather permitting – the traffic reconfiguration is expected to take place over the weekend of February 18, 2017 and additional lane reductions will be required during the set-up. Once complete, this new set up will remain in place for up to three (3) months.

Traffic will be shifted to the south side of Eglinton Avenue, allowing work to proceed on the north side. Utility relocations at the northwest and southwest corners and road widening continue and piling on the north side of Eglinton Avenue will begin. Excavation will also begin for the off-street bus terminal at the northeast corner. 

Hours of Work

  • Work zone set-up will begin as early as February 17, 2017 and take up to approximately one (1) week to complete. Once complete, this set up will remain in place for up to three (3) months. 
  • Most of the work is expected to be performed between 7:00 AM and 7:00 PM, however the contractor is permitted to work between the hours of 7:00 AM and 11:00 PM, 7 days a week. The contractor may not always work during the permitted hours, but may do so at its discretion. 
  • Limited overnight works may also be expected. Updates on works taking place during overnight periods will be communicated separately.  
  • Work is subject to permits and all relevant approvals, and may be rescheduled due to weather conditions or unforeseen circumstances.

Traffic and Pedestrian Details

The weekend of February 18, 2017 (weather permitting)

  • Eglinton Avenue East and Don Mills Road will be reduced to a minimum of one lane of traffic in each direction.
  • Right turns from eastbound Eglinton Avenue to southbound Don Mills Road will be prohibited.
  • Additional turn restrictions may be put in place during this time in order to perform this work safely.
  • Signage will be displayed to advise motorists of turn restrictions.

February 20, 2017 up to Spring 2017

  • A minimum of two lanes of through traffic will be maintained in all directions.
  • The existing right turn on red restriction from southbound Don Mills to westbound Eglinton will remain in place.
  • All crosswalks at the intersection will be open. 
  • All existing sidewalk closures and detours remain in effect for this stage. Pedestrian detours are clearly marked with signage directing pedestrians to the alternate routes.

TTC Details

  • All existing bus stop relocations remain in place for this stage.
  • Relocation and re-routing of bus stops is done in consultation between TTC and Metrolinx to ensure construction can continue safely while minimizing impact on the community and customers. Please watch for posted notices indicating new information.

For more information, please contact Heather Glicksman at the East Community Office.

Thank you for your patience as we work to build this important project.

 Please support your local businesses during construction.

Sign up to receive regular email updates.