Water and Sewer Connections at Caledonia Station

 
mai 26, 2017

What Work is Taking Place?

Beginning May 29, 2017, crews will perform temporary water and sewer service connections to the Caledonia Station site.  The work will be carried out in two stages.  Traffic changes will be in effect.  A traffic control person will be present to direct traffic.  Once complete, traffic will return to the existing staging.

Hours of Work

·       Starting May 29 for approximately one (1) month.

·       Monday through Sunday, 7:00 a.m. to 11:00 p.m.

·       This work may be rescheduled due to weather or unforeseen circumstances.

Stage 1 – beginning May 29 for approximately 1.5 weeks



Stage 2 – beginning June 8 for approximately 2 weeks

What to Expect

·       Nearby businesses and residents can expect to hear noise caused by construction vehicles and equipment.

·       Pedestrians and motorists can expect delays when travelling through the intersection.

·       A Paid Duty Officer, flag person and support vehicles will be present to direct traffic.

·       As always, please take care when travelling near construction zones.

 

Traffic Changes

·       Lane reductions along Eglinton Avenue West will be in effect between Gabian Way and Croham Drive.

·       Sidewalk and pedestrian crosswalk closures will be in effect.

·       The TTC bus stop on the north side of Eglinton Avenue West at Blackthorn Avenue will be temporarily unavailable at times during this work.

 

Please Contact Us

If you would like more detail about this work or any other aspect of the Eglinton Crosstown project, please contact Carlos Hernandez at (416) 782-8118.

 

Thank you for your patience as we work to build this important project.