Support of Excavation at Mount Pleasant Station

 
juin 21, 2018

 

What Work is Taking Place?

As early as June 21, crews will mobilize a drill to the southeast work zone and begin piling on the south side of Eglinton Avenue East.  Piling is a common step in the process of constructing the foundation of a building, in which crews will drill several meters below-grade, a steel beam is placed in the shaft and concrete is poured.  Piles form the support of the station structure.  Following pile installation, lagging, braces and tie-backs will be installed to support excavation.

Once storm sewer operations on the southwest side of Eglinton Avenue are complete, piling will commence there with a drill rig operating east and west of Mt Pleasant Road, simultaneously.

Piling will be completed during permitted hours.  Noise from drilling activity can be expected.

Current Construction Staging

Hours of Work

  • Beginning as early as June 21, 2018 for approximately four (4) months
  • Permitted construction hours are 7:00 a.m. to 11:00 p.m., Monday to Sunday

What to Expect

  • Noise from construction activity and equipment can be expected
  • Dust from drilling activity can be expected
  • Installation of additional fencing, dust cloth, concrete barriers and scaffolding may be installed
  • Property access will be maintained.

Traffic Details

  • The current construction stage will remain in place for the start of piling activity, however anew construction stage will be implemented in the coming weeks

 

Disponible en francais

 

For more information, please contact Natalie Ardanaz at the East Community Office.

Thank you for your continued patience as we work to build this important project.