Intersection Closure for Pile and Decking Installation at Chaplin Station

 
octobre 25, 2018

 

What Work is Taking Place? 

As early as October 29, crews will conduct a closure of Chaplin Crescent between Eglinton Avenue West and Spadina Road in order to complete piles and decking installation.  Due to the location of the piles at station headwall in the middle of the intersection, Chaplin Crescent must be closed to vehicular traffic while this work takes place, TTC and emergency vehicles excepted.  One lane of traffic on Eglinton Avenue West will be maintained in each direction.

This work will take approximately three (3) weeks to complete. Upon completion, a new traffic stage will be implemented.

Construction Staging

Traffic set-up for Chaplin closure

Details

  • As early as October 29, 2018 for approximately three (3) weeks
  • 7:00 a.m. – 11:00 p.m., Monday through Sunday

What to Expect

  • Chaplin Cres will be closed between Spadina Rd and Eglinton Ave W
  • Access for TTC, emergency services vehicles, and local access will be maintained
  • A concrete deck will be installed over top of the work area upon completion
  • Road users can expect delays when travelling through the intersection
  • This work may be rescheduled or delayed due to unforeseen circumstances or inclement weather

Future Construction Staging

Upon completion of this work the following construction staging will be implemented

Chaplin work zone

 

 

For more information, please contact Kyle Reaburn at the West Community Office.

Thank you for your continued patience as we work to build this important project.