Lane Reductions at Caledonia Station December 14 - 15, 2019

 
décembre 13, 2019

What Work is Taking Place?

On Saturday, December 14, crews at Caledonia will be receiving a wide-load delivery of rebar. Westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way from as early as 2:00 PM on Saturday, December 14 until Sunday, December 15 at 3:00 PM.

Hours of Work

  • Saturday, December 14 until Sunday, December 15
  • Lane reductions will begin at approximately 2:00 PM and last for approximately 25 hours
  • In the event of inclement weather, work may be rescheduled

What to Expect

  • Noise from the rebar delivery truck and equipment can be expected
  • Motorists can expect delays when travelling through the intersection
  • One westbound lane on Eglinton Ave may be occupied while this work takes place
  • There will be no impacts to pedestrian routes or TTC stops

Construction Staging

Lane Reductions at Caledonia Station on Dec 14 & 15 2019