Update: Extended Hours for Excavation at Chaplin Station March 9-14, 2020

 
mars 10, 2020

 

What Work is Taking Place?

 

Since fall 2019, excavation has been underway at Chaplin Station.  Excavation of the Tertiary Entrance shaft is now complete, and excavation continues at the Main Entrance, located on the north side of Eglinton Avenue between Chaplin Crescent and Gilgorm Road (the former Chaplin Parkette), as well as beneath the station roof.  Using excavators, soil is removed from the station box and entrances, and loaded into dump trucks that haul the excavated soils to an off-site facility.  Beginning Monday March 9, 2020, excavation and hauling will take place 24 hours through Saturday March 14, 2020.

Work Map Area

Hours of Work

  • Excavation and hauling will take place 24 hours Monday March 9 – Saturday March 14, 2020
  • After March 14, excavation will resume Monday – Sunday, 6:00 a.m. – 12:00 midnight
  • Construction hours are subject to change; overnight work may be required in the future

What to Expect

  • Overnight noise from construction activity can be expected
  • Staging of dump trucks on the median on Chaplin Cres north of Spadina Rd
  • Motorists can expect delays when travelling through the intersection

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

 

Disponible en français

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.