REVISED: North Service Parking Lot Expansion at Kennedy Station
Original Post: July 31, 2020
Updated on August 4, 2020
What Work is Taking Place?
Crews will be expanding the TTC North Service Parking Lot north of Eglinton Avenue East at Kennedy Station. This work will take place through to late August 2020. Work may take place between 6:00 a.m. and 5:00 p.m., Monday to Friday.
What to Expect
Crews will be removing existing asphalt, excavating, backfilling, grading and paving. Crews will endeavor to perform less noisy work during early morning hours and site-based noise mitigation measures will be implemented.
TRAFFIC IMPACTS
• No changes to the existing traffic configuration.
PEDESTRIAN IMPACTS
• No changes to the current pedestrian routes.
HOURS OF WORK
• Work will take place through to late August 2020
• Work may take place between 6:00 a.m. and 5:00 p.m., Monday to Friday.
• Work may be rescheduled due to unforeseen circumstances
OTHER IMPACTS
• Minimal noise from construction equipment and crews can be expected.