Utility Crossing Work and Track Resurfacing at Kennedy Station's GO Corridor April 2-4, 2021
What Work is Taking Place?
Crews at Kennedy Station continue with GO corridor development, including utility installations. From Friday April 2 until Sunday April 4, crews will be installing utility casing crossings within the GO track area, followed by track resurfacing. Crews will be working from as early as 6:00am until 11:00pm.
What to Expect
Installation of utility casing includes the use of excavators, front end loaders, rollers, tampers, and track resurfacing equipment. Crews will be excavating to install the casing, welding the casings together, and then refilling and levelling the area with fresh granular material and compaction of the material into the ground. The track resurfacing equipment will then run along the track alignment. Noise from construction equipment caused by loaders, trucks, and other machinery, as well as dust and debris removal. Crews will be using a roller to perform backfilling and compaction works. Vibrations can be expected.
HOURS OF WORK
- Crews will be working from Friday April 2 until Sunday April 4
- Crews will be working from 6:00am until 11:00pm
- Work may be rescheduled due to weather conditions or unforeseen circumstances
- The contractor may not always work during the permitted hours but may do so at its discretion
- This work may take longer or shorter than expected
TRAFFIC DETAILS
- All current traffic restrictions will remain in place
PEDESTRIAN DETAILS
- All current pedestrian restrictions will remain in place
- Access to businesses and properties will be maintained