Concrete Pour at Cedarvale Station - May 12, 2021
What Work is Taking Place?
As early as Wednesday, May 12, 2021, crews will perform a concrete pour within the work zone between Park Hill Road and Allen Road South. To ensure the integrity and continuity of the pour, work will begin as early as 4:00 a.m. and take approximately twelve (12) hours to complete. One concrete pump will be set up within the work zone. During the pour, concrete trucks will stage in the laydown area east of Allen Road South. Traffic control personnel and/or a Paid Duty Officer will be present while this work takes place.
Expect delays while travelling through the intersection. 4+ concrete trucks are expected per hour. Noise from concrete trucks and pumps can be expected.
HOURS OF WORK
- As early as Wednesday May 12, 2021
- The pour will begin as early as 4:00 a.m. and will take approximately twelve hours (12) to complete
- This work may be rescheduled or delayed due to inclement weather or unforeseen circumstances
TRAFFIC & PEDESTRIAN DETAILS
- No changes to the traffic configuration or pedestrian routes are expected as a result of this work
TTC INFORMATION
- Access to TTC will be maintained at all times