November 162017

Gantry Crane Delivery and Installation at Avenue Station Secondary Entrance

What Work is Taking Place?

Beginning Wednesday November 22, a large overhead Gantry Crane will be delivered to Avenue Station and installed at the Secondary Entrance site.  

Several truckloads of large steel columns that the overhead crane will sit on will be delivered to the site.  Due to the size of these deliveries, trucks will be backed-in to the existing construction zone east of Avenue Road through the west gate.  Short traffic interruptions can be expected while these deliveries take place. Read more »

November 152017

REPOST & UPDATE: Avenue Station Sewer Lining

Original Issue Date: October 14, 2017
Repost & Update Date: November 15, 2017

 

Beginning as early as November 20, 2017.

Sewer lining work takes place on a 24 hour schedule.

WHAT WORK IS TAKING PLACE? Read more »

November 022017

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on November 1, 2017. You can see the presentation here:

Read more »

October 252017

Avenue Station Construction Updates - October 25

CONSTRUCTION ACTIVITIES AT AVENUE ROAD

Construction activities outside the long-term set up continues to be active as we prepare for upcoming mining operations. These activities are happening during the daytime and nighttime, and overlap. Residents and businesses can expect to see the following daytime and nighttime work at various locations in the roadway or on the sidewalk.

THIS WEEK AT AVENUE STATION: Read more »

October 182017

Avenue Construction Updates - October 18

Construction Activities at Avenue Road and Eglinton

As we gear up to begin mining operations at the Secondary Entrance in November, there are many other parcels of preparatory work to complete. Construction outside of the long-term set up is very active and will be for the rest of the year.

Residents and businesses can expect to see many works happening at various locations in the roadway or on the sidewalk, often at the same time.

  Read more »

October 132017

Chaplin and Avenue Stations Open House

Thank you for attending the open house about Chaplin and Avenue Stations on October 12, 2017. 

For those of you who missed it, the presentation is here: Read more »

October 122017

Sewer Lining Activities at Avenue Station - Bypass Installation & Lining Operations

SEWER LINING AT AVENUE STATION

The entire sewer lining process will take approximately 4 – 6 weeks to complete.

Sewer bypass work takes place in the daytime construction hours.

Sewer lining work takes place on a 24 hour schedule.

WHAT WORK IS TAKING PLACE? Read more »

October 102017

Mining at Avenue Station

Mining is expected to begin in November 2017, and will carry on through to late 2019.

What Work is Happening?

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.” 

Excavation of the entrances at Avenue Station is nearing completion and mining will begin soon. Read more »