Avenue Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
June 182020

Avenue & Chaplin CLC - Presentation Deck - May 6, 2020

Construction Liaison Committee of Avenue & Chaplin was held on May 6, 2020. You can see the presentation here.

May 082020

Inner Wall Demolition at Avenue Station

What Work is Taking Place? 

Mining excavation is nearing completion at Avenue Station, with crews breaking-out the remaining inner walls between Eastbourne Avenue and Lascelles Boulevard.

Intermittent wall demolition works will continue through to approximately late-May 2020, with crews operating 24-hours a day, five (5) days a week. Once these works are complete, permanent works, including final lining and concrete pours, will commence east of the secondary entrance. Read more »

May 082020

UPDATE:Concrete Pour at Avenue Station: May 11, 2020

What Work is Taking Place? 

As early as May 11, 2020 crews will perform a concrete pour at the main entrance of Avenue Station. The concrete will form one of the permanent station structures underground. To safely carry out the works, westbound traffic on Eglinton Avenue West will be reduced to one lane at the Main Entrance. The pour will begin at 10:00 a.m. and take approximately five (5) hours to complete.  After each pour is complete, the lane will re-open.

  Read more »

April 212020

UPDATE: Extension of Inner Wall Demolition at Avenue Station: Monday, May 4, 2020

What Work is Taking Place? 

Mining excavation works continue at the secondary entrance of Avenue Station, with crews operating between Eastbourne Avenue and Lascelles Boulevard. As part of these works, crews are required to break away the temporary inner walls of the cavern, to finalize the station structure. Read more »