Avenue Road
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Line Painting at Avenue Station
Crews will refresh the crosswalk line markings on Eglinton Ave W between Oriole Parkway and Braemar Avenue. East/west crosswalks and north/south crosswalks will be refreshed.
To minimize disruption, this work will occur overnight.
HOURS OF WORK/ WHAT TO EXPECT Read more »
Central West Open House (Fairbank to Eglinton Stations)
Thank you for attending the Central West Open House on March 18, 2019. For those of you who missed it, the presentation is here:
Short Duration Water Shut Off - Avenue Station
Short Duration Water Shut Off
Sunday March 3rd, 10:00 p.m. to 6:00 a.m.
WHAT WORK IS TAKING PLACE?
Crews at Avenue Station will complete minor works on a local water main from approximately 10:00 p.m. on Sunday March 3rd to 6:00 a.m. on Monday March 4th.
During the works, there will be a temporary water shut off that will last up to ten (8) hours. During this time, there will be no water available from the taps or toilets. Read more »
Test Isolation of a Watermain
WATERMAIN ISOLATION
WHAT WORK IS TAKING PLACE?
On December 20th, crews will perform a test isolation of a watermain located between Oriole Parkway and Eastbourne Avenue. There are no known services connected to this main and thus no anticipated impacts however should you experience a disruption please contact Crosstown Community Office 24 hours at 416-782-8118.
TIMING Read more »
Central West Open House (Cedarvale, Forest Hill, Chaplin, Avenue and Eglinton)
Thank you for attending the open house about Cedarvale to Eglinton Stations on November 12, 2018. For those of you who missed it, the presentation is here:
Watermain Lining Work Avenue Station
UPDATE: WATERMAIN LINING & TEMPORARY WATER SERVICE
AVENUE STATION SECONDARY ENTRANCE
WHAT WORK IS TAKING PLACE? Read more »
Construction Notice - Additional Monitoring Wells at Avenue Station
DATE: Additional Monitoring Wells at Avenue Station
WHAT WORK IS TAKING PLACE?
Over the next two weeks, crews will work to install additional monitoring wells required for Avenue Station, east of the Secondary Entrance. The wells will be installed in the area around Eglinton Avenue W and Oriole Parkway. These wells support the ongoing monitoring instruments installations required during the construction of Avenue Station. Read more »
Avenue Station Construction Updates
MINING UPDATE
Mining operations are underway at both the Secondary Entrance and the Main Entrance sites. Mining occurs on a 24 hour schedule. Starting in early September, mining will occur on a 24 hour schedule, 7 days a week. Read the construction notice for more detail.
Secondary Entrance Read more »