July 122019

Early Work at Forest Hill Station - Saturday July 13, 2019

What Work is Taking Place?

Crews will pour concrete at the Secondary Entrance site of Forest Hill on Saturday July 13, 2019.  To ensure the integrity of the concrete, crews will begin work at 5:00 a.m., avoiding peak temperatures. Work will take place within existing construction zones.

Details  Read more »

July 052019

CANCELLED: Lane Reductions for Overnight Concrete Pour at Forest Hill Station Wednesday July 4, 2019

**Please note that this work has been CANCELLED - An updated notice will be posted when a date is confirmed.**

Originally Posted: June 25, 2019 

Updated: July 5, 2019

What Work is Taking Place?

On Thursday July 4, 2019 beginning at 3:00 a.m. crews will perform a concrete pour at Forest Hill Station. The concrete will form part of the roof of the future station. Lane reductions will be in effect for concrete truck staging.  Read more »

June 172019

CANCELLED - Intersection Closure for Overnight Concrete Pour at Bathurst St and Eglinton Ave W - June 21, 2019

What Work is Taking Place?

An intersection closure of Bathurst Street and Eglinton Avenue West is required to complete a large concrete pour, which will form part of the roof at Forest Hill Station. The closure has been confirmed for Friday June 21st, 2019; with a rain date of Friday June 28th, 2019.

There will be a second closure for an additional concrete pour in July 2019. The date of the second proposed closure will be confirmed in a future notice. Read more »

June 032019

Proposed Intersection Closure for Overnight Concrete Pour Bathurst St and Eglinton Ave W - June 2019

What Work is Taking Place?

Two (2) intersection closures of Bathurst Street and Eglinton Avenue are being proposed to complete two large concrete pours. The first closure, pending approval, would take place in June and the second in July 2019. The concrete will form part of the roof of Forest Hill Station.  

The first proposed closure is scheduled for Friday June 21st, 2019.  The date of the second proposed closure will be confirmed in a future notice. Read more »

April 252019

Updated: Overnight Work at Forest Hill Station April 27-28, 2019

What Work is Taking Place?

Since March 2019, crews have been performing overnight hydro utility work at Forest Hill Station. On Saturday April 27, 2019, crews will perform overnight geotechnical investigation work at the Main Entrance, located on the northeast corner of Bathurst Street and Eglinton Avenue. This work involves, drilling of boreholes in various locations. 

Details Read more »

March 052019

Overnight Lane Reductions at Forest Hill Station March 2019

What Work is Taking Place?

Starting March 11, 2019, overnight lane reductions will resume at intersection of Bathurst Street and Eglinton Avenue West while crews perform works at Forest Hill Station.  Activities will include, installation of hydro utility infrastructure and drilling of boreholes in various locations throughout the intersection.  Read more »

January 222019

Updated: Resumption of Overnight Wet Utilities Work at Forest Hill Station January 24, 2019

What Work is Taking Place?

Crews have been completing overnight wet utility and hydro utility installation work at Forest Hill Station since September 2018; this work will continue through until mid-February 2019. 95% of all utilities relocation and installation work at Forest Hill Station have been completed.

Resuming January 24, 2019, overnight water main chamber construction will commence on Eglinton Avenue, east of Bathurst Street. Traffic in the vicinity of the work area will be reduced to one (1) lane only, alternating in each direction.  Read more »

January 182019

Overnight Traffic Change at Forest Hill Station

What Work is Taking Place? 

As early as January 20, 2019, a new traffic configuration will be implemented at Forest Hill Station.  Traffic on Bathurst Street will be shifted to the east side, and traffic on Eglinton Avenue will remain on the south.  This configuration will be in place for approximately three weeks until early February 2019.  Pile installation, excavation and utilities work will continue through winter 2019. Read more »

January 162019

Overnight Traffic Change at Forest Hill Station

Originally Published: January 7, 2019

Updated: January 16, 2019 

What Work Is Taking Place? Read more »