Bayview Avenue

Looking for updates near a specific intersection?

Choose an intersection from the drop down list to view all of the latest news and construction updates in that area. Intersections are listed from west to east with Eglinton as the main cross-street.




Syndicate content
 
July 212017

UPDATE: Overnight Crosswalk Removal and Re-Painting at Leaside Station

What Work is Taking Place?

Leaside station is required to do a refresh to the existing crosswalk painting at the Bayview Ave and Eglinton Ave E intersection. Due to the volumes of traffic in the area and existing construction set up reducing available lanes, these works will be completed overnight.  Read more »

July 192017

UPDATE: Support of Excavation Works at Leaside Station

What Work is Taking Place?

In early 2017, crews began drilling at the Main Station Entrance site as part of the support of excavation work, also known as shoring.  Drill work in the main station area has been completed. The drill machine will now be moved to the Secondary entrance site on the north west corner of Bayview Avenue and Eglinton Avenue East. Read more »

July 132017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on July 12, 2017. You can see the presentation here:

Read more »

July 102017

Water Main Investigations at Leaside Station

What Work is Taking Place

Crews will expose the portions of a water main on the north east corner of the Bayview Avenue and Eglinton Avenue East intersection. 

Timing  Read more »

June 142017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on June 14, 2017. You can see the presentation here:

May 292017

Temporary Power Connection at Leaside Station

What Work is Happening?

Crews will perform works to complete temporary power connections for the main and secondary entrances for Leaside Station. Work includes hydro pole replacements, switch installations and trenching for underground installations. Short duration hydro outages will occur during these works. If your address is impacted by an outage you will receive a separate notification.

Work will occur in the following locations: Read more »

May 252017

Overnight Line Painting at Leaside Station

What Work is Happening?

A refresh to the existing line painting in the Leaside station area is required. Due to the volume of traffic in the area and existing construction set up reducing available lanes, these works will be completed overnight. 

Line painting will occur at the Bayview Avenue and Eglinton Avenue East intersection as well as Mann Avenue and Eglinton Avenue East intersection.

This work will be completed with hand sprayers. Read more »

May 032017

Hydro Works at Leaside Station

What Work is Taking Place

Crews will perform work on a hydro cable chamber located within the Bayview and Eglinton intersection. All left turns at the intersection will be temporarily prohibited during the work.

Hydro in Intersection at Leaside Station Read more »

March 212017

Dewatering wells at Leaside Station

What Work is Taking Place?

Crews will drill a number of dewatering wells and open a trench to connect the wells along the south side of Eglinton Avenue East from Bayview Ave to 595 Eglinton Avenue East. 

 Read more »