Birchmount Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
July 102019

Update: Eastbound Left Turn Reinstated at Rosemount Drive at Eglinton Avenue East

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work began as early as late February 2019 and will last for approximately nine (9) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

June 192019

Guideway Work at Birchmount Road

Guideway Work Birchmount Road

What Work is Taking Place?

  

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East. As early as July 1, 2019 the construction zone will shift to the centre of Eglinton Avenue East at Birchmount Road and be in place for approximately six (6) weeks. Read more »

June 132019

Weekend Traffic Restrictions at Birchmount Road

Latest Update: July 5, 2019

What Work is Taking Place?

The north side pavement reconstruction works at Eglinton Avenue East and Birchmount Road will be moved to July 6/7 (from June 29/30). The guideway work in the centre of Eglinton Avenue East will now be in place as July 8th.

Hours of Work Read more »

June 102019

Upcoming Hydro Outages

UPDATED: Planned Hydro Outages in June 2019

 

In support of construction of the future Crosstown Light Rail Transit, crews have been upgrading and relocating existing overhead and underground hydro utilities between Birchmount Road and Kennedy Road along Eglinton Avenue East. Outages are required to switch services to the new infrastructure. Read more »

May 312019

Update: Construction Underway for Traction Power Substation 12

Updated: Construction Underway for Traction Power Substation 12

What Work is Taking Place? Read more »

May 292019

Updated: Construction Begins for Traction Power Substation 12

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be commencing construction of the Traction Power Substation (TPSS) 12 that will power the Eglinton Crosstown Light Rail Transit (ECLRT) line. The work will take place in a fenced work zone located on the north east side of Birchmount Road in close proximity to Toronto Police Service 41 Station. Read more »

May 282019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on May 28, 2019. You can see the presentation here:

Read more »

April 302019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on April 30, 2019. You can see the presentation here:

Read more »

April 112019

Eastern Works Open House

Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here:

Download the presentation