December 232020

UPDATE: Closure on Rosemount Drive North of Eglinton Avenue East

Update: Reopening December 21, 2020 – January 11, 2021

What Work is Taking Place?

October 292020

Overnight OCS Cable Works on Eglinton Ave between Birchmount Road and Ionview Road - November 4-5, 2020

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton Avenue East between Birchmount Road and Ionview Road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles).  Installation will take place overnight November 4-5, 2020 between the hours of 9:00 p.m. and 6:00 a.m.

 

What to Expect Read more »

October 222020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late December 2020

 

 

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late December 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work.

 

What to Expect Read more »

October 082020

(Updated) Glazing Installation at Golden Mile, Birchmount, O'Connor and Wynford Stops

UPDATED OCTOBER 23, 2020

What Work is Taking Place?

Shelter installation has been ongoing across the surface alignment for the Eglinton Crosstown LRT, beginning October 26, 2020, crews will perform glazing installation at the Wynford, O'Connor, Golden Mile and Birchmount stop shelters.  Glazing consists of glass Installation works for the LRT shelters.

What to Expect Read more »

September 302020

Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on September 29, 2020. You can see the presentation here:

 


Read more »

September 302020

Overnight Track Works on Eglinton Ave East between Birchmount and Kennedy Road - October 5-9, 2020

 

 

What Work is Taking Place?

Crews will be installing and performing welding activities on the LRT tracks within the guideway work zone on Eglinton Avenue East between Birchmount Road and Kennedy Road. Work will take place October 5-9, 2020 between the hours of 5:00 p.m. and 3:30 a.m.

 

What to Expect Read more »