Black Creek Drive Lane Closures
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
Choose an intersection (A to Z)
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
March 13, 2018
Updated March 13
WHAT WORK IS TAKING PLACE?
Crews will be working within the roadway between at the intersection of Black Creek Drive and Eglinton Avenue West. There will be one (1) long-term median curb lane closure south of Eglinton Avenue and two (2) long-term lane closures north of Eglinton Avenue. This work is expected to last approximately eight (8) months.
TIMING
- Work will occur for approximately eight (8) months, beginning as early as February 20, 2018.
- As early as February 20, 2018 the curbs modifications for widening road turns will occur.
- As early as March 14, 2018 the full closure of the road lines with the installation of the Jersey Barriers will occur.
- The majority of this work will occur between the hours of 7:00 a.m. and 11:00 p.m. daily
- Work may be rescheduled due to weather conditions or unforeseen circumstances.
WHAT TO EXPECT
- Widening of the curbs along the northeast and southwest corner are required to facilitate truck/bus westbound right turns and provide adequate room for receiving traffic.
- Some overnight short-term lane closures will be required for girder erection and installation. Complete closure of Black Creek Drive – two (2) nights 10:00 p.m. to 6:00 a.m. in mid-June 2018
TRAFFIC AND PEDESTRIAN IMPACTS
- North pedestrian crossing at the intersection will be closed.
For more information, please contact Lancefield Morgan at the West Community Office.
Thank you for your continued patience as we work to build this important project.
Please support your local businesses during construction.
Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.
Categories: