Brentcliffe Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
January 142022

Brentcliffe-Victoria Park CLC Meeting - Presentation - January 13, 2022

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.

Read more »

January 062022

Watermain Connection Work – Eglinton Avenue East and Brentcliffe Road

UPDATE: POSTPONED on January 17 till Late January 

Watermain Connection Work –

Eglinton Avenue East and Brentcliffe Road Read more »

November 052021

Brentcliffe-Victoria Park CLC Meeting - Presentation - November 4, 2021

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.

Read more »

August 202021

Noise Barrier Wall and Soil Nail Wall Removal

Rendering

 

As early as Fall 2021, crews will begin removing the temporary noise barrier wall and soil nail wall located on the south side of Eglinton Avenue East, east of Brentcliffe Rd. The temporary walls were erected in 2014 to facilitate the construction of the east portal. Removal of the walls will take approximately two (2) months. 

What to Expect Read more »

June 202021

OCS Cable Installations on Eglinton Avenue East between Laird Drive and Leslie Street

 

OCS Cable Installations on Eglinton Avenue East between Laird Drive and Leslie Street

What Work is Taking Place?