Caledonia Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
June 142019

CONCRETE POUR AT CALEDONIA STATION JUNE 15, 2019

What Work is Taking Place?

On Friday, June 15th 2019, crews at Caledonia will perform a concrete pour. Eglinton Ave W will remain reduced to one (1) lane travelling westbound from Blackthorne Ave to the entry of the Westside Mall. 

Hours of Work  Read more »

June 132019

Update: RAIL DELIVERY & LANE REDUCTION AT CALEDONIA STATION

What Work is Taking Place?

On Monday, June 17th 2019, crews at Caledonia Station will begin unloading and storing the rails for installation in the tunnels. Eglinton Avenue West will be reduced to one (1) lane travelling westbound from Blackthorne Ave to the entry of the Westside Mall for approximately three (3) weeks.

 

Hours of Work  Read more »

May 062019

HYDRANT FLOW TEST AT CALEDONIA STATION MAY 8, 2019

What Work is Taking Place?

On Wednesday, May 8th 2019 at 9:00am, City of Toronto and CTS crews will be performing a hydrant water flow test at the Caledonia site. Construction staging will remain the same.

 

Hours of Work Read more »

March 292019

Western Segment Open House

Thank you for attending the Western Segment Open House on March 28, 2019. For those of you who missed it, the presentation is here:

Download the presentation

December 212018

HAULING AT CALEDONIA STATION DECEMBER 27 & 28, 2018

What Work is Taking Place?

On Thursday, December 27 & Friday, December 28, 2018 crews will be hauling construction materials in and out of the Caledonia site. Trucks will queue at the centre lane on Eglinton Ave W, west of Blackthorne Ave.   

Hours of Work Read more »