Concrete Pour at Eglinton Station - Thursday August 13, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
August 11, 2020

 

What Work Is Taking Place?

On Thursday August 13, 2020, a concrete pour will be carried out at the Eglinton Station work zone located on the southeast corner of Eglinton Avenue West and Duplex Avenue.  The concrete will form part of the station invert slab.  Concrete pumps will be setup within the work zone and concrete trucks will travel eastbound on Eglinton Avenue to Duplex Avenue to deliver concrete to the site.

 

What to Expect

Noise from construction activity, including concrete trucks, concrete pumps and a crane can be expected.  Several concrete trucks will enter and exit the work zone each hour.  Please note that concrete trucks must remain running to allow for continuous turning of the mixer and to discharge concrete. Please review the traffic and transit details below.

 

 

 

Hours of Work

Thursday August 13, 2020 beginning at 4:00 a.m. for approximately eight (8) hours

Work may be rescheduled due to inclement weather or unforeseen circumstances

 

Traffic and Pedestrian Details

No change to the existing traffic and pedestrian configuration at Yonge St and Eglinton Ave and at Yonge St and Berwick Ave is required for this work