November 1, 2019

CONCRETE POURS ON EGLINTON AVENUE EAST

CELESTICA BRIDGE TO THE DON VALLEY PARKWAY

What Work is Taking Place?

Guideway construction is underway along Eglinton Avenue East from the Celestica Bridge to the Don Valley Parkway. To facilitate upcoming guideway duct bank and track slab pours, periodic single lane closures of one (1) eastbound lane will be required on November 4 to November 7, 2019 beginning as early as 5:00 a.m. Temporary lane closures are required for the staging of concrete trucks and pumps.


Timing

  • November 4, 2019 5:00 a.m. – 4:00p.m.

o   Concrete pour and temporary closure of the inner eastbound lane on Eglinton Avenue East between the Don Valley Parkway East and West.

  • November 5, 2019 5:00 a.m. – 4:00p.m.

o   Concrete pour and temporary closure of the inner eastbound lane on Eglinton Avenue East between the Celestica Bridge and Don Mills Road.

  • November 6, 2019 5:00 a.m. – 4:00p.m.

o   Concrete pour and temporary closure of the inner eastbound lane on Eglinton Avenue East between the Celestica Bridge and Don Mills Road.

  • November 7, 2019 5:00 a.m. – 4:00p.m.

o   Concrete pour and temporary closure of the inner eastbound lane on Eglinton Avenue East between the Don Valley Parkway East and West.

  • The contractor may not always work during the permitted hours, but may do so at its discretion.
  • Work may be rescheduled or extended due to weather conditions or unforeseen circumstances.

What to Expect

  • Concrete barriers will be temporarily removed to access guideway work zone for concrete pour.
  • Periodic single lane closures of one (1) eastbound or lane to accommodate the staging of concrete trucks and pumps.
  • Guideway construction includes cutting and removal of asphalt, excavation, installation of subgrade materials, duct bank and track drainage installation, and track slab and stop construction.
  • Pedestrians and road users can expect delays when travelling through the work zone. As always, please take care when travelling near work sites.

Traffic Impacts

  • Temporary closures of the inner eastbound lane on Eglinton Avenue East between the Celestica Bridge and the Don Valley Parkway East.

TTC Impacts

  • There will be no impacts to existing TTC stops.