June 27, 2019

Construction Update at the Wilson Brook Culvert

WHAT WORK IS TAKING PLACE?

Work on the Wilson Brook Culvert has been underway since late August 2018 on Eglinton Avenue East. Crews are building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. The culvert is located on Eglinton Avenue East between Sloane Avenue and Jonesville Crescent.

Traffic lanes will be realigned (depicted below) as early as Saturday, June 29, 2019.

As support of excavation continues, compaction will commence as early as July 2, 2019 and continue for one week. Pile installation will begin as early as July 8, 2019 and continue for approximately two weeks. Excavation and remaining construction activities will then continue until late September, 2019.


TIMING 

  • Traffic lanes will be realigned as early as June 29th, 2019.
  • Compaction will begin as early as July 2, 2019 and continue for approximately one week.
  • Pile installation will begin as early as July 8, 2019 and continue for approximately two weeks.
  • Work is expected to occur from 7:00 a.m. to 5:00 p.m., seven (7) days per week, Monday through Sunday.
  • The contractor may not always work during the permitted hours, but may do so at its discretion.
  • Work may be rescheduled due to weather conditions of unforeseen circumstances.

WHAT TO EXPECT

  • Nearby residents and businesses can expect noise and vibration around the work area caused by compaction, pile drill and other construction equipment.  
  • Monitoring will be conducted to ensure all levels are kept within industry standards.