Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
April 082020

Driveway Closures and Boulevard Restoration Works: Rosemount Drive to Kennedy Road - April 20, 2020

 

What Work is Taking Place

As part of the ongoing construction for the future surface alignment of the Eglinton Crosstown LRT, crews will begin driveway tie-ins and boulevard restoration on Eglinton Avenue East, between Rosemount Drive and Kennedy Road. Partial or full driveway closures may be required at some properties along Eglinton Avenue East to ensure that driveways are aligned with the grading of the road.  Read more »

April 072020

Temporary Parking Removal and Lane Closure for Equipment Unloading at Chaplin Station Wednesday April 8, 2020

What Work is Taking Place?

On Wednesday, April 8, 2020, a mobile crane will be delivered to the Chaplin Station Main Entrance site.  The crane will travel north on Chaplin Crescent to Spadina Road, turn onto New Haven Drive and continue south on Gilgorm Road.  The crane will be used to unload equipment from Eglinton Avenue into the site.  Once the equipment has been unloaded, the crane will be removed from the site following the same route.  Read more »

April 072020

Update: Cross Passage 10 at Eglinton Avenue East and Lillian Street

 

What Work is Taking Place?

Excavation of the cross passage at Eglinton Avenue East and Lillian Street is complete. The north and south tunnels are now connected, allowing the next phase of construction to begin. 

Crews will start permanent works within the cross passage, forming the final structure of the corridor since mid-March. Permanent works, including rebar installation, waterproofing, and concrete pours, will take approximately four (4) months to complete. Work will take place on a 24-hour basis.  Read more »

April 032020

Update: Notice of Chipping at Chaplin Station Extended through April 8, 2020

What Work is Taking Place?

Chipping of a concrete pile wall between the Chaplin Station Tertiary Entrance site and the station box is currently underway.  This work is expected to be complete Wednesday April 8, 2020.  Chipping involves use of an excavator and jackhammer to remove concrete and hardened material. Chipping occurs periodically as deep excavation progresses.  Noise and vibration can be expected. Read more »

April 032020

Stop Construction at Ionview Road

 

What Work is Taking Place

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be working on stop construction at Ionview Road, beginning Monday April 6, 2020 and lasting for two (2) weeks. 

Guideway and stop construction includes, cutting and removal of asphalt, excavation, installation of subgrade materials, duct banks installation, track drainage, track slab and stop construction.

 

Work Area Map Read more »