Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
February 262021

Overnight OCS Cable Installation on Eglinton Ave at Laird, Leslie, Sloane & Kennedy. March 1 - April 2

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton avenue east between Laird drive, Leslie street, Swift drive, Sloane avenue, and Kennedy road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles). Read more »

February 232021
February 112021

Scaffolding Installation at Leaside Station's Main Entrance -February 15 2021

 

Traffic Configuration

As early as February 15, 2021, crews at Leaside Station will begin to install a temporary scaffolding system along the east wall of the Main Entrance site to provide overhead protection and delineation for the work zone.  Scaffolding installation will take place within the work zone between 7:00 a.m. – 11:00 p.m. for approximately two (2) days. The scaffolding system will remain in place for approximately four (4) months.

  Read more »

February 112021

UPDATED: Traffic Change at Kennedy Station, East of Kennedy Road - February 11,2021

UPDATE: Photo updated to show current traffic configuration. Work is ongoing until summer 2021.

February 102021

Update: Extended Construction Hours at Leaside Station - February 2021

 

Traffic Configuratoin

Through Summer 2021, crews at Leaside Station will continue to work extended construction hours at the station entrances and in the station box below Eglinton Avenue. Construction activities include waterproofing, placement of rebar and steel, formwork installations, mechanical electrical works, and concrete pours.

  Read more »

February 092021

Concrete Pour at Fairbank Station - February 10, 2021

 

What Work is Taking Place?

Crews at Fairbank Station continue to perform large concrete pours. Crews will be pouring on Wednesday, February 10, beginning as early as 7:00am. Concrete pumps and trucks will be placed on Vaughan Road, adjacent to the Fairbank Station Main Entrance site. Vaughan Road, Dufferin Street, and Eglinton Avenue West will remain open while this work takes place.