March 29 2019

Telecommunication Relocations at Wynford Bridge

 

Telecommunication Relocations at Wynford Bridge  

WHAT WORK IS TAKING PLACE? Read more »

March 29 2019

Overnight Line Painting at Cedarvale Station

What Work is Taking Place?

To accommodate the painting of new traffic lines at the Allen and Eglinton intersection, crews will be working overnight from 2am-5am to minimize impacts to traffic and reduce the risk of incident to crew members. As the current lines are fading, the work is scheduled to occur as soon as possible provided proper weather conditions.

Hours of Work Read more »

March 29 2019

Driveway Access Restrictions for Civil Road Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing civil road work in relation to road widening and curb relocation activities on the south side of Eglinton Avenue East between Pharmacy Avenue and Hakimi Avenue.  Read more »

March 28 2019

Construction Notice: Intersection Closure for Overnight Concrete Pour

Intersection Closure for Overnight Concrete Pour

Chaplin Cres & Eglinton Ave
Saturday April 6, 2019
Read more »

March 28 2019
March 27 2019

Concrete Pour at Fairbank Station - March 29, 2019

What Work is Taking Place?

On Friday March 29, crews will perform a concrete pour at the Main Entrance area of Fairbank Station. The concrete will form part of the Main Entrance walls.  A concrete pump will be placed on Vaughan Road behind the Main Entrance site, and concrete trucks will deliver concrete to the site.  Dufferin Street and Eglinton Avenue West will remain open while work takes place.

Hours of Work Read more »

March 27 2019

Upcoming Bus Route Flips at Kennedy Station to accommodate shoring at the SRT

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, crews will be conducting a series of bus flips in the vicinity of the Scarborough Rapid Transit (SRT) - Line 3 at Kennedy Road. Read more »

March 26 2019

Overnight Utilities Relocations at Pharmacy Avenue and Eglinton Avenue East

WHAT WORK IS TAKING PLACE?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road. Read more »

March 26 2019

Updated: Guideway Work along Surface Section of the Eglinton Crosstown LRT: Thermos Road/Sinnott Road.

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East between Warden Avenue and Birchmount Road. Preliminary work began on March 16, 2019.

Starting as early as April 15, 2019 for approximately six (6) weeks, there will be access restrictions for guideway work in the center of Eglinton Avenue East between Thermos Road and Sinnott Road. Read more »

March 25 2019

Early Start Hauling at Mount Pleasant Station Spring 2019

What Work is Taking Place?

Beginning Tuesday March 26, 2019, crews will begin hauling operations early at 6:30 a.m., Monday through Sunday, while excavation on the south side of Eglinton Ave is underway.  Excavated fill will be removed from the excavated areas by a dump truck and transported to off-site location.

Hours of Work Read more »