May 31 2019

Update: Construction Underway for Traction Power Substation 12

Updated: Construction Underway for Traction Power Substation 12

What Work is Taking Place? Read more »

May 31 2019

Nightly Lane Closures at Fairbank Station - June 2 to June 7, 2019

What Work is Taking Place?

As early as Sunday June 2nd, crews will be reducing Eglinton Ave W from Northcliffe Blvd to Dufferin St to one lane from 8pm – 5am. This work will last approximately one week. The north lane will be closed as early as Sunday June 2nd for two nights, followed by the south lane for three nights. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.  Read more »

May 30 2019

Overnight Utilities Relocations at Eglinton Avenue East and Wynford Drive

Overnight Utilities Relocations at Eglinton Avenue East and Wynford Drive 

WHAT WORK IS TAKING PLACE? Read more »

May 30 2019

Weekend Traffic Restrictions at Hakimi and Lebovic Avenue - June 1-2 & June 8-9

Originally Posted: May 23, 2019 

Updated: May 30, 2019 

What Work is Taking Place? Read more »

May 29 2019
May 29 2019

Updated Traffic Configuration at Swift/Credit Union Drives and Eglinton Avenue East

Updated Traffic Configuration at Swift/Credit Union Drives and

Eglinton Avenue East

  Read more »

May 29 2019

Overnight Concrete Pour at Fairbank Station - May 30, 2019

What Work is Taking Place?

On Thursday May 30th, crews will perform a 650m3 concrete pour at Fairbank Station. The concrete will form the base of the second level concourse at the main entrance. Concrete pumps will be placed in the work zone, and concrete trucks will queue in the southbound lane of Dufferin Street between Eglinton Avenue West and Hunter Street as well as the west curb lane of Vaughan Road. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.  Read more »

May 29 2019

Updated: Construction Begins for Traction Power Substation 12

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be commencing construction of the Traction Power Substation (TPSS) 12 that will power the Eglinton Crosstown Light Rail Transit (ECLRT) line. The work will take place in a fenced work zone located on the north east side of Birchmount Road in close proximity to Toronto Police Service 41 Station. Read more »

May 28 2019

ROAD WIDENING AND PAVING AT SLOANE AVENUE AND EGLINTON AVENUE EAST

WHAT WORK IS TAKING PLACE?

Throughout 2019, Eglinton Crosstown LRT construction will require temporary changes to intersection operations from Credit Union to Ionview for road paving and guideway construction. This work is required for the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East. Read more »