August 28 2019

Truck Staging at Leaside Station

WHAT WORK IS TAKING PLACE?

To facilitate deep excavation currently underway at Leaside Station, construction vehicles will periodically occupy the eastbound curb lane of Roehampton Avenue, west of Bayview Avenue. Truck staging in this location will not block any driveways or entrances to businesses. 

HOURS OF WORK Read more »

August 28 2019

GUIDEWAY CONSTRUCTION AT CREDIT UNION AND SWIFT AVENUE AT EGLITON AVENUE EAST

GUIDEWAY CONSTRUCTION AT CREDIT UNION AND SWIFT AVENUE AT EGLINTON AVENUE EAST 

WHAT WORK IS TAKING PLACE? Read more »

August 27 2019

Update: East Bound Left Turn Temporarily Closed at Rosemount

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews  will continue work with stage 2 at Massey Creek.

Preparatory work began in late February 2019 includes tree removals, dewatering of wells and deep excavation. Crews will be excavating nine and half (9.5) meters deep and replacing the storm water culvert.

UPDATE: 

The east bound left turn will be temporarily closed as of Monday, August 26th due to utility relocation. Read more »

August 27 2019

Tree Removal on Eglinton Avenue East at the West Don River Bridge

WHAT WORK IS TAKING PLACE?

In support of the continued construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East, tree removal is required for four (4) trees in close proximity to the construction zone at the West Don River Bridge. Read more »

August 23 2019

Guideway Construction on Eglinton Avenue East at Leslie Street

WHAT WORK IS TAKING PLACE?

Lanes will be realigned to accommodate guideway construction on Eglinton Avenue East at Leslie St. Traffic is expected to change to the configuration depicted below as early as August 28, 2019 and will remain in place until mid-November, 2019. For this stage, two eastbound-to-northbound lanes will be restored and westbound traffic moved to the north of Eglinton Avenue East. Read more »

August 23 2019

CRANE INSTALLATION Leaside Station Main Entrance

A large tower crane at Leaside Station Main Entrance will be installed over September 3th to 5th. To facilitate the crane installation, the work zone will expand temporarily to the west on Bayview Avenue from September 3nd to September 5th. One lane in each direction will be maintained on Bayview Avenue and southbound and northbound left turns will be restricted during the two days of work. 

  Read more »

August 23 2019

Overnight Water Shut off August 28, 2019 7:00 PM — 5:00 AM at Massey Creek

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, crews will be upgrading and relocating wet utilities.

An overnight water shut off is required during these works.  It will occur on Wednesday August 28 from 7 p.m. – 5 a.m.

 Hours of Work Read more »